Menu
Shutdown Maintenance Strategy: How to Execute a Perfect Turnaround (2026 Guide)

Shutdown Maintenance Strategy: How to Execute a Perfect Turnaround (2026 Guide)

Key Takeaways

 

  • Scope Creep Kills: The #1 reason Shutdowns go over budget and over time is "While You're At It" jobs added at the last minute. You must implement a "Scope Freeze" 4 weeks before the start.

  • The "S-Curve" Tracker: Don't wait until the end of the day to ask "Are we on schedule?" Use software to track % Complete hour-by-hour. If you fall behind on Day 1, you can recover. If you wait until Day 3, you are dead.

  • Contractor Control: Shutdowns bring strangers into your plant. Use Digital Permits to ensure every contractor has the right insurance, safety briefing, and Work Order before they touch a machine.

  • The Vertical Startup: The goal isn't just to finish the repair; it's to restart production at full speed immediately. Fabrico enforces "Pre-Startup Safety Reviews" (PSSR) to ensure no tools are left inside the machine.

Shutdown Maintenance Strategy: How to Execute a Perfect Turnaround (2026 Guide)

Maintenance Shutdown (or Turnaround) is the most high-stakes event in the factory calendar.
You stop production (Zero Revenue). You hire expensive contractors (High Cost). You open up critical machinery (High Risk).

If you finish 4 hours early, you look like a genius.
If you finish 4 hours late, you lose thousands of dollars in missed orders.

Managing a shutdown on a whiteboard or Excel sheet is suicidal. You cannot track 500 tasks and 50 contractors with a marker pen.
You need a Digital Command Center.

Here is the 2026 playbook for executing a flawless Turnaround using Fabrico.

 

Phase 1: The Scope "Deep Freeze"

Success is determined months before the machines stop.
The enemy is Scope Creep.

  • Jan 1: We plan to replace the boiler seal.

  • Jan 15: "Let's also paint the floor."

  • Jan 20: "Let's rebuild the conveyor."

Suddenly, a 2-day shutdown becomes a 4-day shutdown squeezed into 2 days.

The Strategy:

  1. The Digital Backlog: Use Fabrico to tag potential shutdown jobs year-round ("Tag: STO-2026").

  2. The Freeze Date: 4 weeks out, lock the list. No new jobs added without the Plant Manager’s signature.

  3. The Kit Check: Verify that every part for every job is physically on site. If the part isn't there, the job is cut from the scope.

 

Phase 2: The Command Center (Execution)

Once the shutdown starts, "Daily Meetings" are too slow. You need "Hourly Visibility."
If a critical path task (e.g., Crane Lift) is delayed by 30 minutes, everything behind it pushes back.

The Strategy: Real-Time Mobile Updates.

  • The Workflow: Technicians and Contractors don't write reports at the end of the shift. They click "Complete" on their mobile app the second the bolt is tightened.

  • The Dashboard: The Maintenance Manager sits in the "War Room" watching the Fabrico Dashboard.

    • Green: On Schedule.

    • Red: Delay detected on Line 4.

  • The Reaction: You see the Red delay instantly. You reallocate resources from Line 2 to Line 4 to catch up.

 

Phase 3: The "Stranger Danger" (Contractor Safety)

Shutdowns mean strange faces on the shop floor. Contractors are 3x more likely to have accidents because they don't know your hazards.

The Strategy: Digital Gatekeeping.
Use Fabrico to manage the external workforce.

  • Permit to Work: The contractor cannot start until they complete the digital safety permit on the tablet (Hot Work, Confined Space, LOTO).

  • Task Assignment: They receive a specific Work Order. They cannot wander around "looking for work."

  • Verification: They must upload a photo of the finished job before your supervisor signs off on their hours.

 

Phase 4: The Vertical Startup

The most dangerous moment is the restart.

  • Are all the tools removed?

  • Are the guards back on?

  • Is the oil refilled?

 

If you miss one thing, the machine crashes on startup ("Infant Mortality"), and your shutdown was a failure.

The Strategy: The PSSR (Pre-Startup Safety Review).
Create a mandatory "Go/No-Go" Checklist in Fabrico.

  • Check 1: Verify LOTO removal.

  • Check 2: Verify tool count (5 in, 5 out).

  • Check 3: Bump test motor.

 

Only when the checklist is 100% green does Operations get the "All Clear" to start production. This ensures you ramp up to full speed immediately (Vertical Startup) without stuttering.

 

Conclusion: Orchestrate the Chaos

A shutdown is a symphony. You are the conductor.
If you can't hear the musicians (lack of data), the music falls apart.
Use software to keep everyone in tempo.

Master the turnaround.
 

[Request a Demo] and use Fabrico to plan your next shutdown.

Latest from our blog

Define Your Reliability Roadmap
Validate Your Potential ROI: Book a Live Demo
Define Your Reliability Roadmap
By clicking the Accept button, you are giving your consent to the use of cookies when accessing this website and utilizing our services. To learn more about how cookies are used and managed, please refer to our Privacy Policy and Cookies Declaration