Book a demo
TEEP vs OEE: Total Effective Equipment Performance Explained

TEEP vs OEE: Total Effective Equipment Performance Explained

TEEP explained: the formula, a worked weekly example, TEEP vs OEE and utilization, and how Fabrico, an MES and OEE platform, helps.
TEEP vs OEE: Total Effective Equipment Performance Explained

Key takeaways

  • TEEP (total effective equipment performance) shows how much of all calendar time a machine spends making good parts at full speed.
  • The formula is TEEP = OEE × Utilization, where utilization is planned production time divided by all time.
  • OEE tells you how well you use the time you schedule. TEEP tells you how much of the machine's total capacity you actually turn into good output.
  • Your shift pattern sets a hard ceiling: a machine that runs one 7.5-hour shift, five days a week, can never exceed a TEEP of 22.3%.
  • Use OEE to run the plant every day. Use TEEP before you add shifts or buy new equipment.

TEEP vs OEE: the short answer

OEE measures how well a machine uses the time you planned it to run. TEEP measures the same good output against every hour on the calendar, so it also counts the nights, weekends and holidays you did not schedule. Because TEEP = OEE × utilization, TEEP is always equal to or lower than OEE, and the gap between the two is capacity you have not scheduled.

MetricWhat it measuresTime baseWhen to use it
OEEGood output at ideal speed, as a share of what the planned time allowsPlanned production timeEvery shift and week: find and fix losses on the line
UtilizationThe share of the calendar you scheduled for productionAll time, 24/7Planning: how much of the week is already committed
TEEPGood output at ideal speed, as a share of all calendar timeAll time, 24/7Capacity decisions: a new order, an extra shift, a new machine

Trade press uses the same split. Plant Services (23 March 2026, accessed 16.11.2026) describes OEE as a measure of equipment when it is scheduled to run, and TEEP as the extension that adds total calendar time. Academic work agrees: in an open-access chapter, Iannone and Nenni (University of Salerno and University of Naples Federico II, 2013, accessed 16.11.2026) define TEEP as OEE × loading time ÷ calendar time. They note that utilization covers all calendar hours, which makes it the more useful measure for capacity planning.

One machine, one weekIllustrative, sample dataAll time: 168 h (100%)Planned: 75 h (utilization 44.6%)Fully productive: 51 hOEE 51 / 75 = 68%. TEEP 51 / 168 = 30.4%
OEE divides good time by the 75 planned hours. TEEP divides the same 51 hours by all 168 hours in the week.

Do not mix TEEP utilization up with the capacity utilization rate in national statistics. The US Federal Reserve G.17 release of 16 October 2026 (accessed 16.11.2026) put manufacturing capacity utilization at 75.9% in September 2026, 2.3 points below its 1972 to 2025 average. That rate compares output with sustainable capacity across an industry. It is not scheduled hours divided by calendar hours on one machine.

Track OEE and downtime in real time
Book a demo

What is TEEP? Meaning and definition

TEEP stands for total effective equipment performance.

It measures the share of all time, 24 hours a day and 7 days a week, that a machine spends producing good parts at its ideal speed.

A TEEP of 100% would mean a machine ran perfectly, around the clock, every day of the year.

TEEP uses the same losses as overall equipment effectiveness (OEE). It adds one more: the time you did not schedule at all.

The TEEP formula

TEEP = OEE × Utilization

Utilization = Planned production time ÷ All time

Some sources call this ratio the loading rate, so you may also see TEEP = OEE × Loading.

Some tools use "machine utilization" for run time ÷ available time, which is a different number.

Because OEE is fully productive time divided by planned production time, the two formulas combine into one:

TEEP = Fully productive time ÷ All time

TermMeaning
All timeEvery hour in the period: 168 hours in a week, 8,760 in a 365-day year
Planned production timeThe time you scheduled the machine to produce, after breaks and other time with no production planned are removed
UtilizationPlanned production time as a share of all time
Fully productive timeGood parts at ideal speed, with no stops

TEEP vs OEE vs utilization

The short answer at the top sets out the time base of each metric. This table adds the question each one answers and who uses it.

MetricWhat it measures and who uses it
OEEMeasured against: Planned production time
Question it answers: How well did we use the time we scheduled?
Used by: Production and maintenance teams
UtilizationMeasured against: All time
Question it answers: How much of the week did we schedule?
Used by: Planning and plant management
TEEPMeasured against: All time
Question it answers: How much of the week produced good output?
Used by: Plant management, finance, capacity planning

For the utilization side, read machine utilization vs OEE.

The TEEP time model

TEEP starts with the whole calendar and removes one layer of loss at a time.

LayerWhat is removed to get hereType of loss
All timeNothing yet
Planned production timeNights, weekends, holidays, breaks, no ordersSchedule loss (utilization)
Run timeBreakdowns, changeovers, waiting and other longer stopsAvailability loss
Net run timeSlow cycles and short stopsPerformance loss
Fully productive timeTime spent making bad partsQuality loss

The first layer is set by the schedule and demand. The other three are equipment and process losses, the ones OEE measures.

The six big losses sit inside those three layers.

TEEP calculation example: one machine, one week

A machine runs two shifts, five days a week. Each shift has 7.5 hours of planned production time after breaks.

ItemValue
All time24 × 7 = 168 hours
Planned production time2 × 7.5 × 5 = 75 hours
OEE for the week68%

Step 1: utilization

Utilization = 75 ÷ 168 = 44.64%, or 44.6% rounded

Step 2: TEEP

TEEP = 68% × 44.64% = 30.4%

Step 3: check it with time

Fully productive time = 75 hours × 68% = 51 hours.

51 ÷ 168 = 30.4%. The two methods agree.

What the number means

Out of 168 hours in the week, the machine's good output equals 51 hours of perfect running.

Another 93 hours were never scheduled. The other 24 were scheduled but lost to stops, slow running and defects.

Using TEEP for a capacity decision

Suppose demand is rising and the plant needs more output from this machine. There are three main options.

OptionPlanned hours per weekOEETEEP (fully productive hours)
Today75 h68%30.4%
(51.0 h)
A. Raise OEE by 10 points75 h78%34.8%
(58.5 h)
B. Add two shifts on Saturday and Sunday (4 × 7.5 h)105 h68%42.5%
(71.4 h)
C. Add a third shift on weekdays112.5 h68%45.5%
(76.5 h)

Options B and C assume the new shifts run at the same 68% OEE, which night and weekend shifts often do not. The UK Health and Safety Executive notes that night workers are particularly at risk of fatigue, because their day sleep is often lighter and shorter, and that fatigue can lead to errors, accidents and reduced productivity (HSE, Fatigue, accessed 16.11.2026).

Option A adds 7.5 productive hours a week without adding a shift. Our guide on how to improve OEE shows how.

Options B and C add more hours, but every one of them needs people, energy and supervision.

Most plants should do A first, because improving OEE also makes every added shift more productive.

Buying a second machine usually makes sense only once both levers are close to their limits.

What the three options cost: TEEP in money

The capacity table above counts hours. A plant manager has to defend the choice in money, so here is the same machine priced with public labour cost data. The machine, the shifts and the OEE are the sample figures from the example above. The crew size and the number of production weeks are assumptions: replace them with your own.

InputValueWhere it comes from
Planned hours today75 h a weekExample above: two 7.5-hour shifts, 5 days
OEE68%Example above
Crew per shift3 operatorsAssumption
Labour cost per hour€40.3Eurostat, euro area industry, 2025
Production weeks a year48Assumption

The labour cost is the euro area average for industry in 2025, the highest-paying sector, as published in Eurostat hourly labour costs (accessed 16.11.2026). It includes non-wage costs such as employer social contributions, which is what a shift really costs the plant.

Step 1: the cost of one good hour from a new shift

One crew hour costs 3 × €40.3 = €120.90. A new shift at the same 68% OEE turns each crew hour into 0.68 hours of fully productive time, so one good hour bought that way costs €120.90 ÷ 0.68 = €177.79, before any weekend or night premium.

Step 2: price options B and C

OptionExtra good hours a weekExtra crew cost a weekA year (48 weeks)
A. Raise OEE by 10 points7.5 hNo extra crew hoursThe cost of the improvement work
B. Weekend shifts, 30 h20.4 h30 × €120.90 = €3,627€174,096
C. Third weekday shift, 37.5 h25.5 h37.5 × €120.90 = €4,534€217,620
Extra good hours a week, and crew costIllustrative, sample data, 3-person crewA: OEE +10 points+7.5 h, no extra crewB: weekend shifts+20.4 h for €3,627 a weekC: third weekday shift+25.5 h for €4,534 a week
Bars show extra fully productive hours a week. Crew cost uses the Eurostat 2025 euro area industry labour cost of €40.3 an hour, before premiums.

Step 3: what option A is worth

Option A adds 7.5 good hours a week inside shifts you already pay for. Buying the same 7.5 hours through extra shifts would cost 7.5 × €177.79 = €1,333 a week, or about €64,000 a year over 48 weeks. That is the crew cost you avoid, and the most the OEE work could cost while still beating a new shift on labour alone, before energy, supervision and premiums.

The ten points keep paying if you add a shift later. At 78% OEE each crew hour yields 0.78 good hours, so a good hour costs €120.90 ÷ 0.78 = €155.00, about 13% less than at 68%. That is the arithmetic behind "fix OEE first".

What the labour figure leaves out

  • Premiums. Weekend and night rates come from your own agreement. The Eurostat average does not include them.
  • People. In 2025 only 18.5% of EU employees usually worked at weekends, according to Eurostat (1 May 2026, accessed 16.11.2026). A weekend crew often means hiring or volunteers, not a rota change.
  • Night rules. Under the EU Working Time Directive, the normal hours of night workers must not exceed an average of eight hours in any 24-hour period, and night workers are entitled to a free health assessment before the assignment, as the EU-OSHA summary of Directive 2003/88/EC sets out (accessed 16.11.2026). A third shift brings those duties with it.
  • Demand. Extra good hours only earn money if you can sell what they make. Value them with your own contribution margin, and only for products with orders behind them.

To build the full business case, use our OEE ROI calculation. To price the time a running line loses, see cost of downtime per minute.

This week: pull three numbers

  1. Planned hours per week for your bottleneck machine, from the shift plan.
  2. Last month's OEE on the same machine, with the planned-time rule written down.
  3. Your loaded cost per crew hour from finance, with weekend and night premiums.

With those three, the tables above become yours: what one extra good hour costs, and what each OEE point is worth before anyone asks for a new shift or a new machine.

How to improve TEEP

TEEP has two levers: raise OEE inside the hours you already run, or plan more hours.

Start with OEE, as in option A above, because every hour you add later inherits it.

The ceiling your schedule sets

Even with a perfect 100% OEE, TEEP cannot be higher than utilization.

  • One 7.5-hour shift, five days: maximum TEEP 22.3%
  • Two shifts, five days: maximum TEEP 44.6%
  • Continuous 24/7 operation with no scheduled downtime: maximum TEEP 100%

That is why a low TEEP is not automatically bad. It often reflects a deliberate schedule, not a failing line.

What is a good TEEP?

There is no universal benchmark for TEEP, because it depends mostly on how many hours you choose to run.

A continuous-process plant running around the clock can reach a much higher TEEP than a one-shift job shop with the same OEE.

Use these comparisons instead:

  • Against your own history, with the same schedule.
  • Against your schedule ceiling, to see how much of the scheduled capacity you actually use.
  • Across machines that make the same product, to find where capacity is hiding.

For OEE targets, see world-class OEE.

Two published examples, side by side

Plant Services (31 March 2026, accessed 16.11.2026) works a week in which 28 hours go to planned maintenance and changeovers: loading is 140 ÷ 168 = 83%, OEE is 49%, and TEEP is 83% × 49% = 41%.

Set it next to the two-shift machine on this page: 44.6% × 68% = 30.4%. The plant with the much lower OEE has the higher TEEP, because it schedules 140 hours instead of 75. That is why TEEP compares schedules, and OEE compares how well the line runs inside them. Use both before you call either plant good or bad.

When to use TEEP and when to use OEE

DecisionBetter metric
Which loss should we fix this week?OEE
How did the line perform on this shift?OEE
Can we take a new customer order without new equipment?TEEP
Should we add a shift or weekend work?TEEP
Should we buy another machine?TEEP, then OEE
Which plant has spare capacity for a new product?TEEP

How to measure TEEP

If you already measure OEE, you are most of the way there.

  1. Measure OEE for the machine, with a clear definition of planned production time. Our OEE calculation guide shows how.
  2. Record the schedule: which hours were planned for production, and why the rest were not.
  3. Use calendar time as all time, every hour of the period, including nights, weekends and holidays.
  4. Calculate utilization and TEEP for the same period as your OEE, usually a week or a month.

It helps to split the unscheduled time into reasons: no orders, no staff, planned maintenance shutdowns, holidays.

That split turns TEEP from a single number into a list of capacity decisions.

Common TEEP mistakes

  • Using TEEP to judge the line team. They do not control the schedule, so use OEE for that.
  • Leaving time out of "all time". All time is the full calendar, so removing holidays from it measures something else.
  • Moving maintenance in and out of planned time. Decide once whether a maintenance window sits inside or outside planned production time, then stick to it.
  • Ranking plants by TEEP when their demand differs. A plant with fewer orders will usually schedule fewer hours, whatever its equipment is like. Use TEEP to find spare capacity, not to grade plants.
  • Confusing utilization with availability. Utilization is about the schedule, while availability is about stops during the schedule.

TEEP, OEE and OOE together

OOE (overall operations effectiveness) sits between the two. It measures against operating time, which also includes time that was scheduled and then dropped, for example for lack of orders.

Many plants track OEE daily and review TEEP monthly. Our OOE guide explains when the third metric is worth adding.

If TEEP shows large unused capacity, read our guide to the hidden factory to put a value on it. Choosing a tool? Read our guide to OEE software.

How Fabrico helps

Fabrico is a cloud-based MES and OEE platform for manufacturers, with maintenance management (CMMS) built in.

It records run time, stops and counts from PLCs and IoT sensors, and AI cameras (an add-on) count output where a machine has no usable signal. OEE is calculated in real time for every connected machine, and the operator adds the stop reason at the line.

It also detects micro stops and reports downtime, MTTR and MTBF, so the equipment side of TEEP is measured rather than estimated.

Add the hours you planned, from your own schedule, and you have every input TEEP needs.

See your real-time OEE and downtime on a live dashboard: book a demo. More guides are in our OEE explained hub.

Frequently asked questions

What does TEEP stand for?

TEEP stands for total effective equipment performance.

It measures fully productive time as a share of all calendar time.

How do you calculate TEEP?

Multiply OEE by utilization, where utilization is planned production time divided by all time.

You can also divide fully productive time by all time. Both give the same answer.

What is the difference between TEEP and OEE?

OEE measures against planned production time. TEEP measures against all time, so it also shows the hours you never scheduled.

TEEP is always equal to or lower than OEE.

Can TEEP be higher than OEE?

No. Utilization can never exceed 100%, so TEEP can never exceed OEE.

They are equal only when every hour of the period is planned production time.

What is a good TEEP score?

There is no standard benchmark, because TEEP depends on your shift pattern.

Compare TEEP with your schedule ceiling and with your own history instead.

What is the difference between utilization and TEEP?

Utilization only shows how much of the week you scheduled.

TEEP shows how much of the week actually produced good output, so it also includes stops, speed losses and defects.

See how Fabrico unifies OEE and maintenance in one platform.

Request a demo
Track OEE and downtime in real time
See where lines lose time
Book a live demo.
See where lines lose time
See where lines lose time

Real Fabrico tiles, sample data.

By clicking the Accept button, you are giving your consent to the use of cookies when accessing this website and utilizing our services. To learn more about how cookies are used and managed, please refer to our Privacy Policy and Cookies Declaration