Predetermined Motion Time Systems: MTM, MOST and How to Check a Standard
In short: A predetermined motion time system (PMTS) sets the time for a manual task without a stopwatch. The analyst breaks the task into basic motions such as reach, grasp, move and position, looks up a fixed time for each motion in the system's tables, and adds them up. MTM (Methods-Time Measurement) and MOST (Maynard Operation Sequence Technique) are the best-known systems.
- Times are in TMU: 1 TMU = 0.00001 hour = 0.036 seconds. Standard time = normal time x (1 + allowances).
- PMTS works before the job exists, needs no performance rating and forces a close look at the method.
- Studies have found PMTS times up to 17 to 22% shorter than measured times, so check a standard against real counts before you use it to judge people or lines.
Guide, updated 14 November 2026. Sources are listed at the end.
What is a predetermined motion time system?
A predetermined motion time system is a work measurement method that builds the time for a manual job from tables of basic motions. Course material from India's NPTEL programme (IIT lecture 11 on work measurement) defines it as a procedure that analyses any manual activity in terms of the basic or fundamental motions needed to perform it. Each motion has a preset time, and the times are added to give the time for the whole task.
The idea is that a reach of a given length, to a given kind of destination, takes about the same time for any trained worker working at a defined pace. If that is true, you do not need to watch someone do the job to know how long it should take. You need a description of the method and the tables. That is why PMTS sits close to standard work: the analysis is a written record of one agreed method, with a time attached.
That makes PMTS different from the other work measurement techniques:
- Stopwatch time study times a worker on the job, then rates their pace against a standard pace. It needs a running job and an analyst's judgement of speed.
- Work sampling takes random observations to estimate the share of time spent on each activity. It suits long, irregular work, not short repetitive cycles.
- Standard data reuses element times from earlier studies for similar work.
- PMTS synthesises the time from motion tables. It works on paper, from a drawing or a mock-up, before the job runs.
How PMTS works, step by step
The method is the same across systems. Lecture slides from King Saud University's industrial engineering course set it out for MTM:
- Describe the task in basic motions. The analyst writes down each motion in order, with the variables that change its time: distance, the kind of destination, weight, and whether the left and right hands move at the same time.
- Look for a better method first. The slides make the point that the standard should not be calculated until the task has been broken into elements and checked for improvements. A PMTS analysis is also a method study.
- Look up the time for each motion in the system's tables.
- Add them up to get the normal time: Tn = the sum of the motion times.
- Add allowances for personal needs, fatigue and delays, according to company policy: Tstd = Tn x (1 + allowance).
The unit of time is the TMU, the time measurement unit. The same slides, and notes from Eastern Mediterranean University's work study course, define it as one hundred-thousandth of an hour:
- 1 TMU = 0.00001 hour = 0.0006 minute = 0.036 second
- 1 second = 27.8 TMU
- 1 minute = 1,667 TMU
- 1 hour = 100,000 TMU
The small unit is deliberate. The original TMU values came from studying motion pictures of work, frame by frame, and a single short reach takes only a fraction of a second.
The basic motions
The Eastern Mediterranean University notes list the MTM-1 elements and what drives their time:
- Reach: moving the hand or fingers to a destination. Time depends on the length, the kind of destination and the type of reach.
- Move: carrying an object to a destination. Time depends on the same factors plus a weight factor.
- Turn: rotating the hand, wrist and forearm, empty or loaded. Time depends on the degrees turned and the weight.
- Grasp: getting enough control of an object to do the next motion.
- Position: aligning, orienting and engaging one object with another. Time depends on the class of fit, symmetry and ease of handling.
- Release: letting go, either by opening the fingers or as a contact release.
- Apply pressure, eye times and body motions cover the rest.
The King Saud slides note that many of these elements correspond to the therbligs that Frank Gilbreth defined in his motion studies, with changes and additions to suit MTM.
The main systems: MTM, MOST and others
There is not one PMTS but a family. The NPTEL lecture lists four early systems with their years: Work-Factor (1938), Methods-Time Measurement (1948), Basic Motion Time (1951) and Dimension Motion Time (1954).
MTM: Methods-Time Measurement
MTM was developed by Maynard and others in the late 1940s, according to a paper by Liang Ma and colleagues in Human Factors and Ergonomics in Manufacturing (2010). MTM-1 is the original and the most detailed level, on which the other MTM systems are based. Higher levels trade detail for speed of analysis, as the King Saud slides describe:
- MTM-1 works at the level of basic motion elements: reach, grasp, move, position, release.
- MTM-2 combines them into motion aggregates. GET combines reach and grasp; PUT combines move and position.
- MTM-3 has four categories: handle, transport, step and foot motions, and bend and arise.
Other MTM systems were added for clerical work, machine shop work and electronic testing, and several computerised versions exist.
MOST: Maynard Operation Sequence Technique
MOST is a simplified system developed from MTM. Instead of single motions, it uses fixed sequence models. Ma and colleagues describe three motion groups:
- General move: moving an object freely through the air.
- Controlled move: moving an object that stays in contact with a surface or attached to another object, such as a lever or a sliding part.
- Tool use: using common hand tools, such as fastening or cutting.
A general move is described with four parameters: action distance (A), body motion (B), gain control (G) and placement (P). Each parameter is given an index from the data card, and the time is T = 10 x index x TMU. With 1 TMU = 0.036 seconds, the time resolution of MOST is 10 TMU, or 0.36 seconds. That coarser grain is the trade: larger blocks are quicker to analyse, at the cost of detail on very short motions.
Advantages and limits
The NPTEL lecture lists what PMTS is used for: setting job standards, comparing methods before production starts, estimating labour, equipment and space, planning assembly line layouts before they run so less rebalancing is needed later, and checking direct time studies.
Its advantages:
- Times can be set from drawings before the job exists.
- No performance rating is needed, which removes the most argued-over step of a time study.
- The analyst has to study the method in detail, which often shows improvements.
- The analysis is a detailed record of the method.
- Basic times are relatively consistent.
Its limits, from the same lecture:
- It covers only the manual part of a job. Machine time, process time and waiting are outside it.
- It needs trained analysts.
- It still needs judgement at several stages.
How accurate are predetermined times?
This is where a plant manager should pay attention. A 2024 study from Polytechnique Montréal, published by AHFE Open Access, tested MOST in the lab. Twenty participants did 300 simple motions each, 6,000 in all, timed with a wrist accelerometer. The findings:
- The authors cite earlier studies of MTM-1, MOST and MTM-UAS that found deviations of up to 17% between predetermined times and measured actual times.
- In their own experiments, the mean MOST estimate was 2.33 seconds against 3.09 seconds from Fitts' law, a standard model of movement time. The authors describe MOST as underestimating the Fitts' law times by 22%.
- The MOST data cards did not account for object weight, motions at shoulder height or differences in distance within the reach zone, which they suggest explains part of the gap.
- They warn that predetermined times which are too short can lead to wrong productivity estimates and, when used to set pace, to overexertion and a higher risk of injury.
That does not make PMTS useless. It makes it a planning tool whose output needs checking against the real line before it becomes a target.
Worked example: a standard for a manual packing station
Example data. A food plant adds a manual end-of-line packing station. Each cycle forms a carton, packs one product with a leaflet, closes it, labels it and pushes it to the outfeed. The TMU values below are illustrative example data, not values read from licensed MTM or MOST data cards; a certified analyst would take them from the system's tables. Only the labour cost comes from published statistics.
| Element | TMU (example data) | Seconds |
|---|---|---|
| Get carton blank, place on fixture | 60 | 2.16 |
| Fold and form carton | 120 | 4.32 |
| Get product, place in carton | 70 | 2.52 |
| Get leaflet, place on product | 50 | 1.80 |
| Close and tuck flaps | 90 | 3.24 |
| Get label, apply | 80 | 2.88 |
| Push carton to outfeed | 30 | 1.08 |
| Total | 500 | 18.00 |
From TMU to a standard
- Normal time: 500 TMU x 0.036 s = 18.0 seconds.
- Allowance for personal needs, fatigue and delays: 15%. Example data; set by company policy.
- Standard time: 18.0 x 1.15 = 20.7 seconds per carton.
- Output per operator hour at standard: 3,600 / 20.7 = 173.9 cartons.
Staffing
The line delivers 600 products an hour to packing. Example data. At standard, that needs 600 / 173.9 = 3.45 operators, so the plan says four people with some slack. The plant runs two 8-hour shifts on 240 days, or 600 x 16 x 240 = 2,304,000 cartons a year. Example data.
The gap, in money
After launch, counts show the four packers average 150 cartons per operator hour. Example data. Against the standard of 173.9, that is a performance of 150 / 173.9 = 86.3%.
- Labour hours a year at standard: 2,304,000 / 173.9 = 13,248 hours.
- Labour hours a year at the actual rate: 2,304,000 / 150 = 15,360 hours.
- Gap: 2,112 hours a year.
The labour cost is $37.21 an hour, the June 2026 employer cost for private industry production occupations, wages and benefits together, in the BLS Employer Costs for Employee Compensation, Table 4. The gap is 2,112 x $37.21 = $78,588 a year on one station. If you count wages only, $25.03 an hour in the same table, it is 2,112 x $25.03 = $52,863 a year. So the gap on this station is worth $52,900 to $78,600 a year, depending on whether benefits move with the hours, and only if the standard is right.
Now test the standard
Before anyone launches a project to recover that money, run the same numbers with the accuracy finding above. If the real time for the job is 17% longer than the predetermined one, the realistic standard is 20.7 x 1.17 = 24.2 seconds, or 148.6 cartons per operator hour. At that standard, the packers at 150 an hour are working at 101%, and the labour gap disappears. Four operators were always the right crew.
The same station, the same counts, and two opposite conclusions: a performance problem worth up to $78,588 a year, or a standard that was too tight. The way to tell them apart is not a debate but data:
- Measure actual cycle times over a full week, by shift and operator, from counts and timestamps.
- Look at the best sustained hour, not the average. If the best crews never get near 174 an hour, the standard is wrong.
- If the best crews do reach it and others don't, the gap is real. Find out what the best crews do differently and write it into standard work.
The point: a PMTS standard is a hypothesis about the method. Measured output tests it.
Book a demo and see OEE and losses per machine and shift.
PMTS and OEE: where the standard meets the line
On a manual or semi-automatic station, the PMTS standard often becomes the ideal cycle time in the OEE calculation. That makes the standard's accuracy a direct input to the performance figure.
- A standard that is too short makes performance look poor every shift, sends teams chasing a loss that does not exist, and can push people to an unsafe pace. The AHFE study makes that safety point directly.
- A standard that is too long hides real slow running and short stops behind a comfortable performance figure.
- A validated standard lets performance loss mean what it says: time lost to slow cycles and small stops.
The sequence that works: set the ideal cycle time from the PMTS analysis, run the station for a few weeks, compare the best sustained rate with the standard, and correct the standard if the two disagree. Only then use the performance figure to drive improvement and line balancing.
PMTS vs other work measurement methods
| Method | How the time is set | Needs the job running? | Strength | Weak point |
|---|---|---|---|---|
| MTM-1 | Basic motions from tables, in TMU | No | Most detail; the base of the other MTM levels | Slow to apply; trained analysts only |
| MTM-2 and MTM-3 | Motion aggregates (GET, PUT; handle, transport) | No | Faster than MTM-1 | Less precise on short, fine motions |
| MOST | Fixed sequence models with index values x 10 TMU | No | Quick; suits longer cycles | Lab study found estimates 22% under a movement-time model |
| Stopwatch time study | Observed time x performance rating + allowances | Yes | Reflects the real workplace | Rating is subjective; needs a running job |
| Work sampling | Random observations, share of time per activity | Yes | Cheap for long, irregular work | Poor for short repetitive cycles |
| Machine counts and signals | Recorded cycles, stops and counts | Yes | Continuous; covers machine time and stops | Says what happened, not how the motions should be done |
In practice the methods work together. PMTS designs the method and sets the first standard. A time study or a week of counted cycles checks it. Continuous counts then show whether the station holds the standard shift after shift.
Common mistakes
- Treating the standard as a fact. A predetermined time is a model. The literature shows gaps of up to 17 to 22% against measured times. Check it before you use it.
- Skipping the method study. Timing a bad method precisely only gives you a precise bad standard. Fix the method first, as the PMTS steps require.
- Forgetting what is outside the analysis. PMTS covers manual motions. Machine cycles, waiting for material, quality checks and changeovers have to be added from other data.
- Using analysts without training. The tables have many variables, and a wrong case or distance class changes the result.
- Ignoring weight, height and reach. The AHFE study found that MOST data cards did not reflect object weight or shoulder-height motions. If the job has them, measure.
- Using the standard to set pace without a safety check. A standard that is too tight pushes people too hard. Ergonomics and pace belong in the same review.
- Never updating it. Every method change, new fixture or product variant changes the motions. The analysis is a record of the method, so update it when the method changes.
For plant, production and CI managers
You may never write an MTM analysis yourself, but your plan, staffing and performance figures depend on the standards that come out of one.
This week
- List the manual stations whose cycle time or staffing comes from a predetermined time standard. Note the date of each analysis.
- For the two largest, compare the standard with last month's counts: actual output per operator hour against the standard rate.
- Find the best sustained hour on each station. If even that is well below the standard, flag the standard for review, not the crew.
- Ask whether the analysis matches the current method, fixtures and product. If anything changed since, the standard is out of date.
This quarter
- Recheck each manual standard against a week of measured cycles. Agree a rule with industrial engineering: if the best crews cannot reach it, the standard is revised.
- Use the validated standards as the ideal cycle times in your OEE figures for manual and semi-automatic stations.
- Price the remaining performance gap in labour hours and money, station by station, and work on the largest first.
- Write the best crew's method into standard work, then repeat the PMTS analysis on that method, so the standard and the method agree.
- Use PMTS for every new station before it is built, then use counts to balance the line once it runs.
Measured cycles are what turn a standard from a guess into a fact. OEE software records counts, run time and stops per station and shift automatically, and a light MES ties them to orders and products, so each standard can be checked against real output without a stopwatch.
How Fabrico fits
Fabrico is a cloud OEE and light MES platform. It shows OEE and losses by machine, line and shift, from the PLC or a Fabrico IoT device, with the reasons operators add on a tablet or phone. That gives you measured cycle counts and performance per station to compare with the predetermined standard.
On manual stations, AI cameras (an add-on) count output.
Book a demo and see good output per line and shift.
What people ask next
Can I set a labour standard for a station that is not built yet?
Yes. That is the main use of a predetermined motion time system: the analyst describes the planned method in basic motions, takes each time from the MTM or MOST tables and adds allowances. Check the standard against measured cycles once the station runs.
Should I use MTM or MOST for my assembly stations?
MTM-1 analyses individual motions such as reach, grasp and position, so it suits short, fine cycles where detail matters. MOST uses fixed sequence models with a time resolution of 0.36 seconds, which is quicker to apply on longer cycles. Whichever you pick, check the result against measured cycles.
How do I convert TMU to seconds and minutes?
1 TMU is 0.00001 hour, so 1 TMU = 0.036 seconds = 0.0006 minutes, and 1 second = 27.8 TMU. A cycle of 500 TMU is 18.0 seconds of normal time before allowances.
My operators never reach the MTM standard. Is the standard wrong or the crew?
Check the best sustained hour over a week of counted cycles. If even the best crews never reach it, review the standard: published studies found predetermined times up to 17 to 22% shorter than measured times. If the best crews reach it and others do not, the gap is real and the best method belongs in standard work.
Can I use a PMTS standard as the ideal cycle time in OEE?
Yes, on manual and semi-automatic stations, once it has been checked against measured cycles. A standard that is too short makes performance look poor every shift; one that is too long hides slow running and short stops.
What does a predetermined time standard not cover?
Only the manual motions. Machine cycle time, waiting for material, quality checks and changeovers sit outside the analysis and have to come from machine data, time studies or work sampling.
Sources
All sources accessed on 14 November 2026. Dates are the publication dates shown on each page.
- NPTEL (IIT), Work measurement, Lecture 11: Predetermined motion time systems, undated, accessed 14 November 2026
- King Saud University, Industrial Engineering, Predetermined Motion Time Systems part 2: Methods-Time Measurement, undated, accessed 14 November 2026
- Eastern Mediterranean University, IENG 301 Fundamentals of Work Study and Ergonomics, Predetermined time systems: Methods-Time Measurement, spring 2019-2020 term, accessed 14 November 2026
- Ma, Zhang, Fu, Guo, Chablat and Bennis, A Framework for Interactive Work Design based on Digital Work Analysis and Simulation, Human Factors and Ergonomics in Manufacturing 20(4), 2010
- Mazareinezhad, Sekkay and Imbeau, Evaluating the Accuracy of the MOST Predetermined Motion Time System Through Lab Experiments, AHFE Open Access vol. 146, 2024
- US Bureau of Labor Statistics, Employer Costs for Employee Compensation, Table 4, June 2026, 9 September 2026