OEE in butter production: churn and packing machine

OEE in butter production: churn and packing machine

OEE of the butter forming and packing machine: churn waits, pack size changes, foil and temperature. Example: 1,144 EUR per shift.
OEE in butter production: churn and packing machine

In short

  • Butter goes from the churn straight to the forming and packing machine. OEE is read from that machine, because it makes the good packs.
  • The temperature of the butter sets the pace. Soft butter smears on the mould, hard butter cracks. Both cause short stops.
  • In the example below, the shift loses 1,144.00 EUR. The largest item is the changeover from the 250 g pack to the 125 g pack.
  • The fat left in the buttermilk is a separate account. OEE does not see it, and it is milk that was paid for.

OEE in butter production is the share of planned time in which the forming and packing machine makes good packs, weighed and sealed. The losses covered here are waiting for butter from the churn, pack size changeovers, stops at the wrapping foil, short stops when the butter is too soft or too hard, and rejects for torn foil and weight.

This article is for owners, process engineers and production managers in dairies that make butter on their own line. It shows how to measure the packing machine, how the churn is recorded against it, and a worked example of one shift in euros.

Butter in Bulgarian dairies

According to Eurostat data on dairy products, Bulgaria produced 1.02 thousand tonnes of butter in 2025, using 21.09 thousand tonnes of whole milk (updated 26.11.2026, accessed 27.11.2026). That is about 1,000 tonnes of butter a year for the whole country.

For a dairy this means short runs: butter is made when cream is available and packed in several pack sizes for shops and restaurants. Every changeover weighs more on short runs. When a run is a few thousand packs, half an hour of changeover is a significant part of the run time, not a minor loss.

Track OEE and downtime in real time
Book a demo

From cream to pack

StageWhat happensLosses recorded
Cream ripeningThe cream is cooled and ripened at a set temperatureCream out of spec, delay
ChurnThe cream is churned and the buttermilk is drained offSlow churning, stop for washing
Butter workingThe butter is kneaded, washed and compactedMoisture out of spec
Forming and packingThe butter is dosed, formed and wrapped in foilChangeover, foil, short stops
Case packing and coolingThe packs go into cases and into a cold roomJam, blocked

The definitions of availability, performance and quality follow ISO 22400-2 (accessed 27.11.2026). The core machine here is the forming and packing machine: it decides how many packs come out. The churn is before it and case packing after it. Their stops are recorded as reasons for its downtime.

What butter is by law

Regulation (EU) No 1308/2013, Annex VII, Part VII, defines butter as a product with at least 80 % and less than 90 % milk fat (accessed 27.11.2026). Water is at most 16 % and dry non-fat milk material at most 2 %. The process engineer keeps the fat and the moisture within these limits.

For OEE this matters directly. A pack with moisture above the limit is a reject, even if it is packed cleanly. So the moisture test after working is a stop with its own reason, not a loss hidden under "other".

The churn and the packing machine

The churn works in batches or continuously, depending on the model. In both cases it feeds butter to the packing machine at its own pace. If churning slows down, the machine hopper empties and the machine stops.

On the packing machine this is recorded as "waiting for product" with the sub-reason "churn". Without a sub-reason the report shows the packing machine as the weak spot, while the problem is in the cream or in the churning.

It helps to record the cream temperature for every batch. When churning slows down, temperature is the first thing to check, before the machine.

Butter temperature and short stops

The machine doses the butter and forms it into a block. If the butter is too soft, it smears on the mould and on the foil. If it is too hard, the block cracks at the edges.

In both cases the operator stops for half a minute to clean the mould. These short stops are below the downtime threshold and count as speed loss. If speed loss rises at certain hours, compare it with the butter temperature at the machine infeed.

That is why butter temperature is a number worth recording every hour. It links the churn, the working and the packing in one picture.

Cream ripening

Before churning, the cream is cooled and ripened for hours at a set temperature. If ripening is short, the butter comes out soft and the fat in the buttermilk rises. If it is long, the day's plan shifts. The process engineer sets the ripening time and temperature in the recipe, and the shift supervisor checks them per batch.

So the start of the shift on the packing machine depends on when the cream was set the day before. The setting time and the ripening temperature are recorded per batch. When the churn is late in the morning, these two values show whether the cause is in the ripening.

Washing the churn

The churn is washed between batches and at the end of the day. If washing between batches takes long, the packing machine waits. This wait is recorded with the sub-reason "churn washing", separate from slow churning.

The two cases have different fixes. Slow churning is a question of the cream. Long washing is a question of the procedure and of the people who carry it out. Recorded separately, they go to different owners.

Case packing and the cold room

The packs are placed in cases and go to a cold room. If case packing stops or the cold room is full, the packs pile up and the packing machine has to stop. On the machine this is recorded as "blocked" with a sub-reason for case packing or for the cold room.

Butter in a warm room loses its shape within minutes. So when the line is blocked, packs cannot wait long on the table. A small chilled buffer between the machine and case packing protects both the product and the machine.

The ideal rate per pack size

The 125 g pack is formed faster than the 250 g pack, but it holds half the butter. Set the ideal rate per pack size, or the larger pack shows a speed loss that does not exist. A good rule is to make the ideal rate the best sustained rate reached for that pack size in a normal shift.

Pack size and the mould change

Butter is sold in 250 g and 125 g packs and in smaller portions for restaurants. Each pack size needs its own mould, a different foil width and a different dosing setting.

A pack size changeover includes changing the mould and the foil reel and checking the weight of the first packs. Set a standard time for each pair of pack sizes. When two orders for the same pack size fall on one day, run them back to back.

Changing the foil for another brand, without changing the mould, is shorter. Keep it as a separate type of changeover, so it does not mix with the long one.

One shift on the packing machine in euros

The numbers are an example, not from a real customer. The machine packs 250 g blocks at an ideal rate of 60 packs a minute. The shift has 450 planned minutes, and a stop longer than 2 minutes is recorded as downtime. The ideal for the shift is 27,000 packs.

At the end of the shift the machine is changed over to 125 g packs, which run on the next shift. All output in this shift is 250 g packs. The contribution per pack is taken as 0.20 EUR. As a reference, data from Aswath Damodaran (NYU Stern) gives a gross margin of 23.23 % for US listed food processing companies (data as of January 2026, accessed 27.11.2026). Replace it with your own price.

CauseStopsMinutesRecorded asPacksEUR per shift
Changeover from 250 g to 125 g1 × 26 min26downtime1,560312.00
Waiting for butter from the churn3 × 7 min21downtime, sub-reason churn1,260252.00
Foil5 × 4 min20downtime1,200240.00
Short stops with soft or hard butter40 × 30 s20speed loss1,200240.00
Rejects: torn foil and weight500 packsquality500100.00
Total875,7201,144.00

How the numbers are reached:

  • Downtime: 26 + 21 + 20 = 67 minutes, run time 383 minutes. Availability: 383 / 450 = 85.1 %.
  • For 383 minutes the ideal is 22,980 packs. Short stops take away 1,200. Packed: 21,780. Performance: 21,780 / 22,980 = 94.8 %.
  • Rejects 500, good 21,280. Quality: 21,280 / 21,780 = 97.7 %.
  • OEE: 85.1 % × 94.8 % × 97.7 % = 78.8 %. Check: 21,280 / 27,000 = 78.8 %.
  • The loss: 5,720 packs × 0.20 EUR = 1,144.00 EUR per shift.
Loss per shift, EURChangeover from 250 g to 125 g312.00Waiting for the churn252.00Foil240.00Soft or hard butter240.00Rejects100.00Example data.
In the example shift, the pack size changeover is the largest item. Example data.

By value, the pack size changeover comes first: 312.00 EUR. It depends on how many times a week the pack size changes. Second is waiting for the churn: 252.00 EUR, a loss that comes from the cream and from the churning.

If each of the 500 shifts in a year (two shifts a day, 250 working days) has one such pack size changeover, it costs 156,000 EUR, and waiting for the churn costs 126,000 EUR. The sums are real only if every lost pack could have been sold; confirm the estimate with the finance department.

Fat in the buttermilk: an account outside OEE

During churning, the buttermilk carries away a little fat. The more fat stays in it, the less butter comes out of the same cream. The good packs come out, and OEE does not see this loss.

The fat in the buttermilk is measured per batch. When it rises, the cause is in the cream temperature, in the ripening or in the churn speed. The process engineer watches this number next to the OEE of the packing machine.

Weight, lot and label

Under Directive 76/211/EEC on prepackaged products (consolidated text of 11.04.2009, accessed 27.11.2026), the tolerable negative error for a 250 g pack is 9 g. The average weight of the batch cannot be below the nominal weight.

Dosing the butter depends on its density, and density depends on temperature. So the checkweigher after the machine shows when the butter has come out softer or harder than normal. More on checkweigher rejects in the article checkweigher rejects and quality in OEE.

The pack carries a lot marking under Directive 2011/91/EU, with the exceptions in Article 2 (accessed 27.11.2026). Milk is listed in Annex II to Regulation (EU) No 1169/2011 (accessed 27.11.2026), and the specific hygiene rules for dairy products are in Regulation (EC) No 853/2004 (accessed 27.11.2026).

Who owns the cream, the churn and the packing

LossOwnerData they need
Waiting for the churnThe process engineerMinutes of "waiting for product" with a sub-reason, cream temperature
Pack size changeoverPlanningMinutes against the standard per pair of pack sizes
FoilThe mechanicStops by reason and by reel
Soft or hard butterThe shift supervisorSpeed loss and butter temperature per hour
Weight rejectsQualityRejects per batch, average weight

Mistakes in recording butter

MistakeWhat shows up laterHow to avoid it
Waiting for the churn is booked as "machine downtime"The packing machine looks like the problem"Waiting for product" with a sub-reason
Butter temperature is not recordedShort stops look randomInfeed temperature every hour
A foil change is booked like a mould changeLong and short changeovers get mixedTwo types of changeover
Fat in the buttermilk is not measuredYield falls with no explanationFat in the buttermilk per batch

Four numbers for the morning meeting

Four numbers from yesterday are enough: OEE of the packing machine, minutes of waiting for the churn, the number of pack size changeovers and the fat in the buttermilk.

If waiting rises, the conversation is about the cream and the churning. If short stops rise, check the butter temperature. Each number goes to the person who can change it. The time the cream was set for ripening shows whether tomorrow morning will start on time.

What to choose for a dairy that makes butter

MethodFits whenWhat it misses
Paper logOne machine, one pack sizeShort stops and sub-reasons
PLC counter into a spreadsheetA first estimateThe reasons and the link to the churn
OEE software with a machine signal and operator reasonsSeveral pack sizes and brandsTemperature and buttermilk, if they are not entered

Questions for the vendor:

  1. How is "waiting for product" recorded with a sub-reason for the churn?
  2. Can the standard changeover time differ for each pair of pack sizes?
  3. Can the butter temperature be entered per hour against the shift?
  4. How is an ideal rate set per pack size?
  5. Is the pack count lost if the plant network goes down?

More on changeover standards in the article changeover standards in FMCG, and on washing the churn and the line in the article CIP time in OEE.

How to start

Five-step diagram for OEE in butter production: machine, churn, temperature, pack size and buttermilk
Five steps for OEE in butter production. Contains no example data.
Text version of the diagram
  1. Read OEE from the forming and packing machine.
  2. Record waiting for the churn with a sub-reason.
  3. Record the butter temperature every hour.
  4. Set a standard for the pack size changeover.
  5. Measure the fat in the buttermilk per batch.

Fabrico provides the measured rates per line; the plan itself is made in the ERP, the APS or the planning spreadsheet.

This week: record the butter temperature at the machine infeed every hour; time one pack size changeover; measure the fat in the buttermilk for three batches.

This quarter: a PLC signal from the machine and operator reasons; a standard per pair of pack sizes; a cream plan arranged around the packing.

Where Fabrico fits

Fabrico is made by the publisher of this article.

  • What it is: an OEE and light MES platform with built-in maintenance management. It shows live OEE per line and shift.
  • Connected line: OEE is read at the core machine, and waiting for product and blocked are recorded as stop reasons.
  • Data: machines connect through the line PLC or through a Fabrico IoT device; where there is no signal, a camera counts the output.
  • Reasons: stops above the threshold get a reason in a few taps, and stops under the set threshold (up to 10 minutes) count as speed loss. The camera does not decide the reason.
  • Money: with the Financial Impact module, every loss has a price in EUR.
  • Video: where a camera covers the line, the video for the minute of a stop opens from the shift timeline, is streamed on request and not stored in Fabrico.
  • Hosting and security: EU customers are hosted on AWS in Frankfurt. Certified to ISO/IEC 27001, ISO/IEC 20000-1 and ISO 9001. The gateway keeps data for up to 30 days if the network goes down.
  • Price: one quote per plant, based on the machines and modules (pricing).

For food plants, see also the article MES for food manufacturing.

A result from a Bulgarian plant

At Ficosota, a maker of home care, hygiene and consumer goods, not food, time with no recorded stop reason fell from 3.20 % to 0.40 % between June and September 2026.

The result comes from 16 lines with OEE and the Financial Impact module, and OEE rose from 53.11 % to 59.62 %. The numbers are approved by the customer.

Ficosota is also an investor in Fabrico (since January 2025) and an industrial partner in developing the OEE module; keep this in mind when reading the results.

See the churn and the packing machine in one shift in Fabrico. In a demo you will see the stops by reason and what each one costs in euros.

Book a demo

Frequently asked questions

Which machine is OEE read from in butter production?

From the forming and packing machine, because it makes the good packs. The churn and case packing are recorded as reasons for its stops.

Whose loss is waiting for the churn?

It belongs to the cream or to the churning. On the packing machine it is recorded as "waiting for product" with a sub-reason.

Why does butter smear on the mould?

Because its temperature makes it softer than normal. Compare the short stops with the butter temperature per hour.

Is the fat in the buttermilk part of OEE?

No. It is a yield loss that is measured per batch and watched next to OEE. When it rises at the same OEE, the cause is in the cream or in the churning.

How much lighter can a 250 g pack of butter be?

Up to 9 g, so down to 241 g. Directive 76/211/EEC allows this error for packs from 200 to 300 g, and the average weight of the batch must be at least 250 g.

How much fat must butter contain?

At least 80 % and less than 90 % milk fat under Regulation (EU) No 1308/2013. A pack outside this range cannot be sold as butter.

Track OEE and downtime in real time
See where lines lose time
Book a live demo.
See where lines lose time
See where lines lose time

Real Fabrico tiles, sample data.

By clicking the Accept button, you are giving your consent to the use of cookies when accessing this website and utilizing our services. To learn more about how cookies are used and managed, please refer to our Privacy Policy and Cookies Declaration