Gable-Top Filler OEE: Losses by Station, CIP Rules and Costs

Gable-Top Filler OEE: Losses by Station, CIP Rules and Costs

Measure OEE on a gable-top carton filler: loss map by station, CIP as planned time or a loss, and a 6,000 carton an hour milk example priced in EUR.
Gable-Top Filler OEE: Losses by Station, CIP Rules and Costs

In short

  • Count it in cartons: OEE on a gable-top filler is good cartons per planned hour divided by the rated cartons per hour for that carton size.
  • CIP standard is planned, overrun is a loss: in the worked example that one rule moves the same day between 72.2% and 80.1% OEE.
  • Map losses by station: blank feed, bottom seal, filling, top seal, cap, coder and the end of line, each tagged A, P or Q with one owner.
  • Leakers outweigh seal stops: in the example, rejected leakers cost EUR 71,820 a year, the seal stop minutes EUR 11,352.
  • Price a minute two ways: EUR 2.365 if the volume is made up in overtime, EUR 10 if the sale is lost.

OEE on a gable-top carton filler is the share of rated output that leaves the filler as good, sealed, coded cartons. A filler rated at 6,000 cartons an hour owes 100 a minute. The number means something only once three rules are fixed: where you count, whether CIP is planned time, and which station owns each stop.

This page sets those rules for chilled and ESL gable-top fillers, maps the losses station by station, decides how to treat CIP with numbers, and prices each loss in a worked example for fresh milk in the Netherlands. Aseptic brick lines have their own sterilisation logic and loss pattern: see the page on aseptic brick lines.

How OEE works on a gable-top filler

The formula is the standard one. The work is in defining each input for this machine, so that every shift counts the same way.

  • Availability = run time / planned production time.
  • Performance = total cartons filled / (run time x rated cartons per minute).
  • Quality = good cartons / total cartons filled.
  • OEE = availability x performance x quality, or simply good cartons / (planned production time x rated cartons per minute).

The short form is the one to check by hand. Take good cartons per planned hour and divide by the rated cartons per hour. If the filler made 4,698 good cartons per planned hour against a rating of 6,000, OEE is 78.3%.

Rated speed: one number per carton size

Use the speed the filler is set up and validated to run for that size and product, written in a table on the line. A 1 L carton and a 0.5 L carton get separate ratings. Changing the rating to make a bad week look better destroys the trend, so the table changes only with an engineering reason.

Count points: total at the filler, good after the last reject

  • Total is cartons filled and sealed, from the filler's own counter.
  • Good is cartons that pass the last check (leak, fill level, code) and go into crates.
  • Blank waste (mis-formed blanks dropped before filling) is packaging scrap. Track it, but keep it out of the product quality rate.

Leakers found later in the cold store or at the customer belong to the shift that filled them. Book them back by date code, or the filler's quality rate looks better than the truth.

Track OEE and downtime in real time
Book a demo

The loss map, station by station

A gable-top filler is a chain of stations in one frame. When it stops, the operator sees one alarm, but the cause sits at one station. Give each station its own stop codes, an A, P or Q tag and one owner, and the weekly review becomes a list instead of an argument.

StationSymptomLossFloor checkOwner
Blank magazine and feedMis-picks, double blanks, blanks that do not openA, PBlank batch, storage time and room conditions, magazine fill levelOperator, packaging QA
Bottom forming and sealingJams on the mandrel, weak bottom sealsA, QSeal settings against setpoint, bottom tear test at start-upMaintenance
Sterilising or sanitising zoneCycle alarm, cycle longer than standardACycle minutes against the validated standard, alarm reasonQA, maintenance
FillingUnder or over fill, foam, product on the seal areaQ, PFill weight samples, product temperature, nozzle dripOperator, QA
Top sealingLeakers, open tops, jams at the sealerA, QSqueeze or tear test after every restartMaintenance
Cap or spout applicatorMissing or skewed caps, feeder jamsA, P, QCap supply level, seating check per hourOperator
Date coderMissing or unreadable codeQ, ACode read at start, after ink or print head workOperator
End of lineFiller stops because crates or pallets back upA (blocked)Log as blocked, not as a filler faultShift lead
SupplyFiller waits for milk from the pasteuriser or buffer tankA (starved)Log as starved, with the upstream reasonProcess
CIP and changeoversCleaning or change longer than standardAActual minutes against the standardQA, shift lead

Two rows in this table decide whether the filler is blamed fairly. Blocked and starved minutes are real availability loss, but the fix sits outside the filler. Keep them as separate codes so maintenance does not chase a crate packer problem inside the filler.

Short stops matter as much as the long ones. A blank feed that hiccups for 20 seconds forty times a shift never reaches the stop log, yet it shows up as lost performance. The page on micro-stops covers how to find them from the machine signal.

One day on a 6,000 carton an hour filler

The worked example is one fresh pasteurised milk filler in the Netherlands, 1 L gable-top cartons, two shifts plus a daily CIP. The numbers are an example built for this page, not a customer's data.

  • Shifts: 2 x 480 minutes = 960 minutes of staffed time. Operators relieve each other, so breaks do not stop the filler.
  • CIP: validated standard 75 minutes, actual 95 minutes, at the end of the second shift.
  • Changeovers: two product changes a day (fat levels), 22 minutes each against a 15 minute standard.
  • Rated speed: 6,000 cartons an hour = 100 a minute for 1 L.
Loss on the dayMinutesType
CIP over standard (95 - 75)20Availability
Changeovers (2 x 22)44Availability
Blank feed and forming stops18Availability
Bottom and top seal stops16Availability
Cap applicator stops14Availability
Blocked by the end of line12Availability
Date coder stops8Availability
Total stop minutes132

The OEE then follows in five lines, each one easy to redo on a calculator:

  1. Planned production time = 960 - 75 (CIP standard) = 885 minutes.
  2. Run time = 885 - 132 = 753 minutes. Availability = 753 / 885 = 85.1%.
  3. Total cartons = 70,000 against 753 x 100 = 75,300 possible. Performance = 92.96%, call it 93.0%.
  4. Rejects = 420 leakers + 180 fill level + 100 coder = 700. Good = 69,300. Quality = 99.0%.
  5. OEE = 69,300 / (885 x 100) = 78.3%.

The 5,300 cartons missing from performance equal 53 minutes at rated speed. They come from slow running after restarts and stops too short for anyone to log. Together with the 132 stop minutes, the filler lost 185 minutes of output on the day.

CIP and sterilisation: planned time or a loss?

This is the rule that most often breaks OEE comparisons between plants and between shifts. Here is the same day under three CIP rules.

CIP rulePlanned timeOEEWhat it hides
All CIP minutes planned (95)865 min80.1%The 20 minute overrun disappears
Validated standard planned (75), overrun a loss885 min78.3%Nothing: overrun shows as availability loss
All CIP minutes a loss960 min72.2%Required hygiene time looks like a breakdown

The checks: 69,300 / 86,500 = 80.1%, 69,300 / 88,500 = 78.3%, 69,300 / 96,000 = 72.2%. Same cartons, same day, almost 8 points apart because of a definition.

Decision: count the validated CIP and sterilisation programme as planned time, and every minute beyond it as an availability loss with its own stop code. Report total CIP minutes per day next to OEE, because they are still capacity the plant pays for.

Why this rule works: the validated programme is a hygiene requirement, not a choice the shift makes. EHEDG guideline 50 on hygienic design requirements for CIP installations covers the "management and validation of hygienic CIP installations". The validated programme is the standard; the overrun is what the shift can fix.

The same logic covers the pre-production sterilisation of an ESL filler. A review of ESL milk processing in the journal Foods describes processors sterilising the filler piping and heads with steam at 120-130 °C for 30 minutes. That cycle is planned time. A cycle that aborts and restarts is a loss.

Where CIP overrun comes from

  • Waiting for the CIP set because another object is being cleaned.
  • A step that repeats after a low temperature or concentration alarm.
  • Late start because the last cartons, the push-out or the hand-over ran long.
  • Waiting for QA release after cleaning.

One rule stays fixed: never chase CIP minutes below the validated programme to lift OEE. Shortening the programme is a validation change for QA, not a performance project for the shift.

Changeovers between products and carton sizes

A gable-top filler sees three kinds of change, and each needs its own standard time. One average "changeover" figure mixes a five minute job with an hour of work and tells nobody what to fix.

  • Product change, same size: whole to semi-skimmed milk, for example. Push-out, flush, first-carton checks.
  • Flavour or allergen change: a rinse or a full clean, depending on what your hazard analysis requires.
  • Carton size change: mechanical work on forming, fill volume, top seal and coder layout, then first-carton checks.

In the example, two product changes take 22 minutes each against a 15 minute standard. That is 44 lost minutes a day, 14 of them over standard. The standard is the target; every changeover minute still counts as availability loss.

Sequence is the cheapest fix. A day planned from plain to flavoured and from allergen-free to allergen-containing products needs fewer rinses. The method for cutting the change itself (separating work done while running from work done while stopped) is on the changeover time page.

Leakers and seal stops: one problem, two losses

A seal problem costs twice. The filler stops while someone adjusts or clears the sealer, which is availability. The cartons that leak get rejected, which is quality. Put both under the seal station, or the review sees two small problems instead of one large one.

The seal is not only a cost issue. Regulation (EC) 853/2004 requires that sealing of consumer packages "must be carried out immediately after filling" in the establishment where the last heat treatment takes place, "by means of sealing devices that prevent contamination". A leaker is a hygiene failure as well as lost milk.

Where leakers start

  • Product on the seal area from nozzle drip or foam.
  • Seal settings drifting after a stop, before the sealer is back at temperature.
  • Board from a blank batch that was stored too long or in the wrong conditions.
  • Worn or dirty sealing parts.

Floor checks that catch them early

  • A squeeze or tear test at start-up, after every stop longer than a few minutes, and after each blank batch change.
  • Leakers counted by hour of the shift. A spike in the first minutes after a restart points at the restart, not at the board.
  • Leakers found downstream booked back to the filling shift by date code.

The coder is the other quality loss with its own pattern. A carton with a missing or unreadable date cannot be sold. The stop and reject patterns of coders have their own page: date coder printer stops.

Shelf life and hygiene rules that shape the numbers

The filler sits between the pasteuriser and the cold store. As an FAO paper on milk packaging puts it, "packaging operations therefore begin at the outlet of pasteurized milk tanks." Everything that goes wrong at the filler happens to a product that has already been heat treated.

  • Recontamination is the risk. Regulation (EC) 2073/2005 sets a process hygiene criterion for pasteurised milk: Enterobacteriaceae at the end of the manufacturing process, 5 samples, limits of under 1 and 5 cfu/ml. Its named action on failure includes a check on "prevention of recontamination".
  • Cold chain: 853/2004 requires milk on acceptance at the plant to be cooled to not more than 6 °C and kept there until processed. Your HACCP plan sets how long pasteurised milk may wait in the buffer tank; a long filler stop can run into that limit.
  • ESL fillers: the Foods review notes ESL milk "is usually not packaged under aseptic conditions" and gives a refrigerated shelf life of 21-45 days. Any post-filling contamination shows up late, at the customer.

Two practical rules follow for OEE. First, if your hygiene plan sets a maximum stop time before the filling zone is sanitised again, that re-sanitise belongs to the stop that caused it. It is not planned time.

Second, a stop that sends milk back to the pasteuriser or into a divert costs product as well as minutes. Log both under the station that caused the stop.

What each loss costs

The prices behind the example, each one named:

  • Labour: Eurostat labour cost levels (lc_lci_lev) give EUR 47.3 per hour for Dutch manufacturing in 2024. The 2025 value is marked confidential in the dataset, so 2024 is the latest published figure.
  • Crew: 3 people on the filler and end of line (sample figure). 3 x 47.3 / 60 = EUR 2.365 per minute.
  • Milk: the ZuivelNL milk price comparison puts the average at EUR 49.83 per 100 kg of standard milk for August 2025. Treating a litre as roughly a kilogram: EUR 0.50 per carton.
  • Pack: blank, cap and coding at EUR 0.07 per carton (sample figure). A scrapped carton costs 0.50 + 0.07 = EUR 0.57.
  • Margin: EUR 0.10 contribution margin per carton (sample figure).
  • Calendar: 25 production days a month, 300 a year. Per shift = half a day.

Milk is a high volume input: CBS reports 13.66 billion kg supplied to Dutch dairy factories in 2024 (provisional). The EUR 0.50 is raw milk only. Standardising, pasteurising and cooling add cost before the filler, so EUR 0.57 per scrapped carton is a floor.

Cost of one filler minute: if the lost cartons are made up in overtime, the minute costs the crew time, EUR 2.365. If they cannot be made up before the delivery slot, the minute costs 100 cartons x EUR 0.10 = EUR 10.00 of margin.

The table prices the day at the overtime rate, the floor value. Euros are rounded; totals come from unrounded figures.

LossShiftDayMonthYear
Leakers, 420 x 0.571202395,98571,820
Other rejects, 280 x 0.57801603,99047,880
Seal stops, 16 min193894611,352
CIP overrun, 20 min24471,18314,190
Changeovers, 44 min521042,60231,218
Other stops, 52 min611233,07536,894
Speed loss, 53 min631253,13437,604
Total, EUR41883720,913250,958
Minutes lost by stationExample: 1 L milk, one daySlow running, micro-stops53 minChangeovers (2 a day)44 minCIP over standard20 minBlank feed and forming18 minBottom and top seal stops16 minCap applicator14 minBlocked by end of line12 minDate coder8 minAmber: speed lossRed: CIP over standard
The example day: 185 minutes of lost output against 885 planned production minutes. Speed loss is shown as equivalent minutes at rated speed. Sample numbers, not a customer's.

Read the table and the chart together. By minutes, changeovers and speed loss lead. By money at the overtime rate, leakers lead: EUR 71,820 a year against EUR 11,352 for the seal stop minutes. The seal station as a whole (leakers plus seal stops) is EUR 83,172, a third of the bill.

The ranking moves when the volume cannot be made up. At EUR 10 a minute, the 185 lost minutes cost EUR 1,850 a day. The 700 rejects cost 700 x (0.57 + 0.10) = EUR 469.

That is EUR 2,319 a day, EUR 57,975 a month and EUR 695,700 a year. Changeovers (EUR 440 a day) then outrank leakers (EUR 281 a day).

So the first question for the plant is not "what is the OEE" but "can a lost minute be made up before the delivery slot?" The answer decides whether the project starts at the sealer or at the changeover.

How to start measuring in two weeks

Most of the value comes from agreeing the rules, not from the tool. Two weeks is enough on one filler if the rules are written down on day one.

Six-step floor card for measuring OEE on a gable-top carton filler, from rated speed to pricing the top three losses
Floor card: six steps to an OEE figure every shift on a gable-top filler counts the same way.
Text version of the diagram
  1. Fix the rated speed: cartons per hour per size, from the validated setting.
  2. Pick one count point: total at the filler, good after the last reject (leak, fill, code).
  3. Split CIP in two: validated minutes are planned time, minutes over standard are availability loss.
  4. Give each station a stop code: blank feed, bottom seal, fill, top seal, cap, coder, blocked, starved.
  5. Time every changeover: product change and size change against their own standard time.
  6. Price the top three losses: leakers at milk plus pack cost, minutes at crew or margin per minute, and review weekly with QA and maintenance.
  1. Days 1-2: write the rated speed table, the count points, the CIP rule and the stop code list. Keep the list under fifteen codes.
  2. Days 3-7: log every stop over two minutes with a code and a station. Count leakers by hour.
  3. Days 8-10: compare the logged minutes with the gap between run time and staffed time. A large unexplained gap means short stops or missing entries.
  4. Days 11-14: price the top three losses with your own labour, milk and margin figures, and pick one to fix first.

If the filler has a PLC with a running signal and a carton counter, use them from day one. Hand counts drift by the second week, and the trend is what you are building.

Choosing how to measure the filler

The options differ in how much the plant learns per hour of effort. Prices for software vary by vendor and scope, so the table gives cost drivers, not list prices.

OptionCost driverFitsWeak spot
Paper sheet and shift reportAbout 15 minutes of operator time a shift: EUR 12 at the Eurostat rateOne filler, first month, agreeing the codesShort stops and speed loss stay invisible
PLC counters and a spreadsheetEngineer days to map signals; ask your integrator for a day rateOne or two fillers with an open PLC and an engineerBreaks when the engineer moves on
OEE software or light MES from machine signalsAsk the vendor for a price per line per monthSeveral fillers, shift-level numbers live, losses in moneyNeeds stop codes and standards agreed first
Full MES with batch recordsA plant project with integration work; quote per sitePlants that need electronic batch records and recipesLong rollout before the filler sees any gain

The third option suits dairy and juice plants with more than one filler. OEE software reads the running signal and counter from the filler, takes stop reasons from the operator and shows availability, performance and quality per shift without anyone typing up a sheet.

What you see: a shift timeline, unclassified time waiting for a reason, and the operator's line-down screen, on sample lines. Book a demo.
Plays from YouTube. Google may set cookies when you press play. Privacy policy.

For a wider comparison of tools by plant type, see OEE software for food and beverage. If batch records, recipes and release steps are on the list too, read the pages on MES for dairy processing and MES for beverage manufacturing.

Who should pick which

Start on paper only if the filler has no PLC access yet and the first job is agreeing what a stop is. Move to software once two or more fillers run, or once leakers and changeovers cost more per month than a line subscription. Choose a full MES when a regulator, customer or group policy requires electronic batch records.

Questions to ask a vendor

  1. Can it read the filler's running state and counter from the PLC, and what is the fallback if the PLC is closed?
  2. Can CIP be set as a planned stop, with the minutes over a standard shown as a loss?
  3. Can each type of changeover be timed against its own standard?
  4. How are leakers and other rejects entered: a reject signal from the line, or a count by hand?
  5. Can losses be priced with each product's selling price and margin?
  6. What happens to machine data when the network drops?
  7. Is the quote per line, per machine or per plant, and what does it include?

Where Fabrico fits

Fabrico is made by the publisher of this article. It is OEE software and a light MES with computer vision. The parts that matter for a gable-top filler:

  • OEE by line and shift from the core machine, the filler, connected through the line PLC or a Fabrico IoT device with sensors.
  • Micro-stops from the machine signal, and stop reasons chosen by the operator at the machine in a few taps, so each station gets its own codes.
  • Planned and unplanned stops kept apart, so CIP and sanitising stay out of the loss while their minutes remain visible.
  • Changeovers tracked against a standard time, and scrap recorded by product and reason (leakers, fill level, coder).
  • With the selling price and margin of each product entered, losses are priced in money and stops are ranked by financial impact.
  • Where a station has no usable signal, the camera add-on counts output.

See the OEE, MES and computer vision features, or how a quote per plant is built on the pricing page.

Sources, accessed 26.11.2026: EUR-Lex, Regulation (EC) No 853/2004, specific hygiene rules for food of animal origin; EUR-Lex, Regulation (EC) No 2073/2005, microbiological criteria for foodstuffs; Eurostat, Labour cost levels by NACE Rev. 2 activity (lc_lci_lev); ZuivelNL and EDF, International milk price comparison, August 2025; CBS, Milk supply and dairy production by dairy factories; EHEDG, Guideline 50, Hygienic design requirements for CIP installations; Deeth, Optimum thermal processing for extended shelf-life (ESL) milk, Foods 6(11):102, 2017; FAO, Packaging, storage and distribution of processed milk.

Frequently asked questions

What is a good OEE for a gable-top filler?

There is no neutral, published benchmark for gable-top fillers. Compare the filler with itself, week by week, under fixed rules for rated speed, count points and CIP. The worked example on this page runs at 78.3%.

Should CIP count as downtime in OEE?

Count the validated CIP programme as planned time and every minute beyond it as availability loss. Report total CIP minutes per day next to OEE, since they are still capacity.

How do I calculate cartons per hour against rated?

Divide good cartons by planned production hours and compare with the rated cartons per hour for that size. In the example, 69,300 good cartons over 14.75 planned hours is 4,698 an hour, 78.3% of 6,000.

Are leakers a quality loss or an availability loss?

Both. Rejected leakers are quality loss; the stops to clear or adjust the sealer are availability loss. Book both under the seal station so the full cost shows in one place.

How long should a changeover take on a gable-top filler?

No neutral standard exists. Set a standard per type of change (product, flavour or allergen, carton size) from your best repeatable result, then measure every change against it.

Is OEE on an aseptic brick filler measured the same way?

The formula is the same, but sterilisation, cycle lengths and loss patterns differ. The page on OEE for aseptic filling lines covers them.

See which filler station costs the most. The demo shows OEE by line and shift from the core machine, stop reasons chosen by operators, planned and unplanned stops, and losses ranked by financial impact.

Book a demo

Track OEE and downtime in real time
See where lines lose time
Book a live demo.
See where lines lose time
See where lines lose time

Real Fabrico tiles, sample data.

By clicking the Accept button, you are giving your consent to the use of cookies when accessing this website and utilizing our services. To learn more about how cookies are used and managed, please refer to our Privacy Policy and Cookies Declaration