Sandwich Production Line OEE: Crew Cards, Changeovers, Giveaway

Sandwich Production Line OEE: Crew Cards, Changeovers, Giveaway

Measure OEE on a crew-paced sandwich line: crew cards, short crew, allergen cleans and giveaway, priced in a UK example at GBP 2,426 of losses a day.
Sandwich Production Line OEE: Crew Cards, Changeovers, Giveaway

In short

  • People set the speed: on a sandwich line the rated speed is packs per minute for one SKU at its standard crew, written on a crew card, not the packer's nameplate.
  • Book a short crew as its own loss: in the worked example the same day reads 44.4%, 66.6% or 69.7% OEE depending on how the rated speed is set.
  • Allergen cleans are the biggest single block: two allergen changeovers take 76 minutes a day, priced at GBP 454 a day in crew time.
  • Giveaway is invisible to OEE: 3 g of extra cheese and 5 g of extra chicken per pack cost GBP 396 a day, more than the short crew.
  • Price a minute two ways: GBP 5.97 in crew time at UK statutory pay floors, or GBP 8.00 of margin if the packs miss the order.

OEE on a sandwich production line is good packs per planned minute divided by the rated packs per minute for that SKU and that crew. A line rated at 40 packs a minute with 20 people on the belt owes 40 good, cut, packed and date-coded sandwiches every planned minute.

The number only means something once three rules are fixed: where the rated speed comes from, how a short crew is booked, and how allergen cleans are counted.

This page sets those rules for chilled food-to-go assembly lines in the UK: bread loading, spreading, filling by an operator crew along a belt, lidding, cutting, wedge packing, labelling and dispatch. It prices each loss in a worked example.

Ready meal lines with depositors and tray sealers have a different loss pattern: see the page on OEE for ready meal production.

How OEE works on a crew-paced line

The formula is the standard one. What changes on a sandwich line is who sets the pace. The belt runs as fast as the slowest station can place its ingredient, and on the example line most stations are people.

  • Availability = run time / planned production time.
  • Performance = total packs made / (run time x rated packs per minute).
  • Quality = good packs / total packs made.
  • OEE = availability x performance x quality, or simply good packs / (planned production time x rated packs per minute).

The short form is the one to check by hand. If the line made 1,599 good packs per planned hour against a rating of 2,400 an hour (40 a minute), OEE is 66.6%.

Where to count

  • Total packs: count at the wedge or skillet packer, the one machine on the line with a reliable cycle signal.
  • Good packs: packs that pass the last check (label and date code, seal, weight or foreign body check) and go into dispatch trays.
  • Bread and filling waste: track it by weight, but keep it out of the quality rate. It is a material loss, not a pack.

Counting at the packer has one weak spot. A sandwich pulled off the belt by QC before cutting never reaches the counter. Count those pulls by hand or with a counter at the end of the assembly belt, and add them to total packs, or quality looks better than it is.

Run time on a belt with people

When the crew goes on a break together, the belt stops. Scheduled breaks are planned time, not a loss. A break that runs over, or a belt that restarts late because people are still putting on clean coats, is availability loss with its own stop code.

Rated speed comes from the crew card

A packer that can wrap 60 packs a minute says nothing about what the line can make. The rated speed is set by the slowest station at a given crew size. Write one card per SKU family: fillings, stations, standard crew, rated packs per minute. Sample cards for one line:

SKU familyFilling stepsStandard crewRated packs/minPacks per person-hour
Simple (cheese and pickle)21445193
Standard (chicken salad)42040120
Layered (club, all-day breakfast)6243075

Sample figures for illustration. Your cards come from time studies on your own line. Packs per person-hour is rated packs per hour divided by the crew: 45 x 60 / 14 = 193, 40 x 60 / 20 = 120, 30 x 60 / 24 = 75.

Why the belt cannot simply go faster

Speeding up the belt with the same crew is not a free lever. The HSE tool for assessment of repetitive tasks (ART) scores "similar motion patterns repeated more than 20 times per minute" in its highest risk band. A person placing one ingredient on every sandwich at 40 packs a minute is well above that.

That is why heavy stations can carry two people sharing one ingredient, and why crews rotate. The ART guidance also warns that rotating between tasks with similar high scores "may not provide enough variation or recovery". The crew card is a safety document as much as a speed table.

So the rated speed changes only when the card changes: a new station layout, a depositor replacing a hand station, or a fresh time study. Raising it to make a bad week look better breaks the trend.

The loss map, station by station

When the belt stops, everybody stops. The cause still sits at one station. Give each station its own stop codes, an A, P or Q tag and one owner, and the daily review becomes a list instead of an argument.

StationTypical lossTypeOwner
Bread loadingBread not delivered, wrong loaf, slices stuckA, PShift lead, goods in
Spreading or butteringSpreader empty, uneven spread, dripsP, QOperator
Filling stationsFilling not ready from prep, empty station, short crewA, PPrep kitchen, shift lead
Lidding and cuttingCutter jams, mis-cut wedgesA, QMaintenance
Wedge or skillet packerFilm or carton jams, open sealsA, QMaintenance
Label and date coderWrong label at SKU change, missing or unreadable codeA, QOperator, QA
Dispatch traysLine blocked by full trays or late chill transferA (blocked)Dispatch lead
ChangeoversRecipe change or allergen clean over standardAShift lead, QA

Two rows decide whether the line is blamed fairly. "Filling not ready" and "blocked by dispatch" are real losses, but the fix sits in the prep kitchen or the chill store. Keep them as separate codes so the line crew is not asked to fix a problem two rooms away.

One day on a 40-pack line

The worked example is one assembly line at a chilled sandwich plant in the UK, two shifts, eight SKU runs on the day, all on the 40-pack crew card. The numbers are an example built for this page, not a customer's data.

  • Shifts: 2 x 480 minutes, each with 45 minutes of scheduled breaks when the belt stops. Planned production time = 2 x (480 - 45) = 870 minutes.
  • Crew: 20 on the belt plus a team leader and a QC checker, 22 people. On shift 2, two people are absent, so 18 stand on the belt.
  • Changeovers: 7 a day. 5 recipe changes at 11 minutes against an 8 minute standard, and 2 allergen cleans at 38 minutes against a 30 minute standard.
  • Rated speed: 40 packs a minute at 20 crew. The card for 18 crew says 36.
Stops on the dayMinutesType
Recipe changes (5 x 11)55Availability
Allergen cleans (2 x 38)76Availability
Filling not ready from prep18Availability
Cutter and packer jams16Availability
Bread supply12Availability
Label and coder stops10Availability
Blocked by dispatch8Availability
Total stop minutes195

The OEE then follows in five lines, each one easy to redo on a calculator:

  1. Run time = 870 - 195 = 675 minutes (375 on shift 1, 300 on shift 2). Availability = 675 / 870 = 77.6%.
  2. Possible at rated speed = 675 x 40 = 27,000 packs. Actual total = 23,600. Performance = 87.4%.
  3. The 3,400 missing packs: 1,200 from the short crew (300 minutes x 4 packs a minute) and 2,200 from slow running and short stops.
  4. Rejects = 220 at assembly QC + 140 at the packer + 60 at the label check = 420. Good = 23,180. Quality = 98.2%.
  5. OEE = 23,180 / (870 x 40) = 23,180 / 34,800 = 66.6%.

The two OEE inputs that change most from day to day here are the number of changeovers and the crew on the belt. Both are decided before the shift starts, which makes them the cheapest losses to attack.

Packs per person-hour next to OEE

On a hand-assembly line, labour is a large cost the plant controls every day, so report it beside OEE. Belt crew hours on the day were 20 x 8 + 18 x 8 = 304. Good packs per person-hour = 23,180 / 304 = 76.3, against 120 on the crew card.

OEE tells the line where its minutes went. Packs per person-hour tells the plant what those minutes cost in people. A day can improve on one and get worse on the other, which is exactly what the review should catch.

Short crew: three ways to book it

Absence is part of life on a food-to-go line. The question is whether it shows up in the numbers. Here is the same day under three rules for the rated speed.

Rated speed ruleOEEWhat it hides
Packer nameplate, 60 a minute44.4%Nothing hidden, but every shift looks broken and nobody uses the number
Crew card at standard crew, short crew booked as a loss66.6%Nothing: the 1,200 packs show up as a short-crew code
Rate rescaled to the crew present69.7%The absence disappears from the line's numbers

The checks: 23,180 / (870 x 60) = 44.4%. 23,180 / 34,800 = 66.6%. For the third rule, possible output becomes 375 x 40 + 300 x 36 = 25,800, performance 23,600 / 25,800 = 91.5%, and OEE 77.6% x 91.5% x 98.2% = 69.7%.

Decision: set the rated speed from the crew card at standard crew, and book every minute run with fewer people as a performance loss under a "short crew" code. The line team cannot fix absence, so report it separately to the people who can: planning and HR.

Rescaling feels fairer to the shift, and that is the problem. Labour planning then never sees that two missing people cost 1,200 packs on one shift.

Changeovers, allergen cleans and chilled life

A food-to-go line can run several SKUs a day against one customer order book; the example runs eight. Changes come in two types, and each needs its own standard time.

  • Recipe change, same allergen profile: swap fillings, labels and film, first-pack checks. Minutes.
  • Allergen changeover: clear the belt, clean and check every contact surface, swap utensils, then first-pack checks. 30 minutes as the standard in the example.

In the example, recipe changes run 3 minutes over standard each (15 minutes a day) and allergen cleans 8 minutes over (16 minutes a day). That is 31 minutes over standard, but 131 minutes of changeover in total. The standard is the target; every changeover minute is still availability loss.

The allergen clean is a control step, not a delay

The Food Standards Agency's allergen guidance for food businesses lists "cleaning utensils before each usage, especially if they were used to prepare meals containing allergens". It also notes "only the 14 allergens are required to be declared as allergens by food law".

So never shorten the allergen clean to lift OEE. Validated clean minutes are a QA decision. Attack the minutes around it: waiting for the hygiene operative, waiting for QA sign-off, hunting for the right label roll.

Sequence is the cheapest fix

A day planned from allergen-free to allergen-containing SKUs, and grouped by allergen, needs fewer full cleans. Cutting the example from two allergen cleans to one saves 38 minutes a day. The method for shortening the change itself is on the changeover time page.

Use-by dates and short runs

Sandwiches carry a use-by date. Under Article 24 of Regulation (EU) No 1169/2011 as it applies in the UK, for highly perishable foods "the date of minimum durability shall be replaced by the 'use by' date". After that date the food is deemed unsafe.

Their life is short. A peer-reviewed study of a hospital listeriosis case in Epidemiology and Infection (McLauchlin et al., 2021) notes that products with a shelf life under 5 days "usually includes sandwiches". The same paper concludes "the most effective intervention will be to prevent contamination at the point of production".

For OEE this has two effects. In the example, packs lost today cannot be made tomorrow, because the order and the life clock have moved on. And the plant makes many short runs to order, so changeovers are a structural loss, not an exception.

Time out of chill during a stop

GOV.UK food hygiene guidance for businesses states: "Chilled food must be kept at 8°C or below." It adds that chilled food can be kept out of the fridge for up to 4 hours, then must be thrown away. Your HACCP plan sets the actual limits for fillings at the belt.

A long stop with fillings in the stations can run into that limit. When it does, the discarded filling belongs to the stop that caused it. Log it under that station, by weight, so the cost of the stop includes the product.

Giveaway: the loss OEE does not see

A sandwich with 44 g of cheese against a 40 g recipe is a good pack. OEE counts it as perfect. The extra 4 g is pure cost, and on a hand-filled line it can be the largest loss nobody reports.

In the example, giveaway is measured by check-weighing filled bases at the start, middle and end of each run (sample figures):

  • Cheese SKUs: 11,800 packs at 3 g over recipe = 35.4 kg a day.
  • Chicken SKUs: 8,000 packs at 5 g over recipe = 40 kg a day.

Priced at the buy price, cheese uses the AHDB UK wholesale price for mild Cheddar: GBP 3,280 per tonne for the latest period at access (weeks 45 to 48 of 2026), about GBP 3.28 per kg.

Cheese giveaway: 35.4 x 3.28 = GBP 116.11 a day. Chicken at GBP 7.00 per kg (sample figure): 40 x 7.00 = GBP 280.00 a day.

That is GBP 396.11 a day, GBP 123,587 a year at 312 production days. For scale, the last ONS average retail price for cheddar, January 2025, was 863 pence per kg. Priced at the wholesale rate, the giveaway figure is a floor.

Where giveaway starts on a hand line

  • Scoops or portioning tools that do not match the recipe weight.
  • New starters on a station without a weighed reference sandwich in view.
  • Speed pressure after a stop: people grab more to keep up.
  • No feedback: weights checked by QC but never shown to the station.

Track giveaway per SKU and station, next to the quality rate, never inside it. The page on giveaway and overfill as a quality loss covers the measurement in more depth.

What each loss costs

The prices behind the example, each one named:

The loaded cost per worked hour follows in four lines:

  1. Annual pay = 12.71 x 39 x 52 = GBP 25,775.88.
  2. Employer NI = 15% x (25,775.88 - 5,000) = GBP 3,116.38. Pension = 3% x (25,775.88 - 6,240) = GBP 586.08.
  3. Total cost = GBP 29,478.34. Worked hours = 39 x (52 - 5.6) = 1,809.6.
  4. Cost per worked hour = 29,478.34 / 1,809.6 = GBP 16.29.

The rest of the price list, all sample figures: GBP 0.85 of bread, fillings and pack per sandwich, GBP 0.20 contribution margin per pack, and 312 production days a year (26 a month). Per shift is half a day.

Cost of one line minute: 22 people x GBP 16.29 / 60 = GBP 5.97 in crew time, if the packs are made up in overtime. If the order ships short instead, the minute costs 40 packs x GBP 0.20 = GBP 8.00 of margin.

The table prices the day at the crew rate, the floor value. Pounds are rounded; totals come from unrounded figures. Short crew and slow running are converted to minutes at 40 packs a minute (1,200 packs = 30 minutes, 2,200 packs = 55 minutes).

Loss, GBPShiftDayMonthYear
Changeovers, 131 min39178220,344244,128
Giveaway, 75.4 kg19839610,299123,587
Other stops, 64 min1913829,939119,269
Rejects, 420 x 0.851793579,282111,384
Slow running, 55 min1643298,541102,497
Short crew, 30 min901794,65955,907
Total1,2132,42663,064756,772
Cost per day by lossExample line, GBP at crew rateChangeovers, 131 min782Giveaway (not in OEE)396Other stops, 64 min382Rejects, 420 packs357Slow running, 55 min329Short crew, 30 min179Red: allergen and recipechanges. Amber: giveaway
The example day costs GBP 2,426 at the crew rate. Changeovers lead, and giveaway, which OEE does not count, comes second. Sample numbers, not a customer's.

Read the table and the chart together. Changeovers are a third of the bill, and the two allergen cleans alone are 76 minutes, GBP 454 a day. Sequencing that drops one allergen clean saves 38 minutes, about GBP 70,816 a year at the crew rate.

The ranking shifts when lost packs cannot be made up, which is common with a use-by date only days away. At GBP 8.00 a minute, the 280 lost minutes (195 stopped, 30 short crew, 55 slow) cost GBP 2,240 a day.

Rejects at material plus margin add 420 x 1.05 = GBP 441, and giveaway GBP 396.

That is GBP 3,077 a day, about GBP 960,059 a year. The short crew alone is then 1,200 x 0.20 = GBP 240 a day of missed margin, before any penalty for a short delivery.

Crew cards to first report: a two-week plan

Most of the value comes from agreeing the rules, not from the tool. Two weeks is enough on one line if the rules are written down on day one.

Six-step floor card for measuring OEE on a sandwich assembly line, from crew cards to pricing giveaway and allergen cleans
Floor card: six steps to an OEE figure that every shift on a sandwich line counts the same way.
Text version of the diagram
  1. Write a crew card per SKU family: stations, standard crew, rated packs per minute.
  2. Count at the packer: total from the packer signal, good after the last label and seal check, QC pulls added by hand.
  3. Book short crew as its own loss: minutes run with fewer people, under a short-crew code.
  4. Split changeovers in two: recipe change and allergen clean, each against its own standard.
  5. Weigh giveaway by station: filled bases at the start, middle and end of each run.
  6. Price the top three losses: minutes at crew or margin rate, giveaway at buy price, and review daily with the shift lead and QA.
  1. Days 1-2: write the crew cards, the count points, the break rule and a stop code list of under fifteen codes, including "short crew" and "filling not ready".
  2. Days 3-7: log every stop over two minutes with a code and a station. Write the crew on the belt every hour.
  3. Days 8-10: compare logged stops with the gap between staffed time and run time. A large gap means short stops or missing entries.
  4. Days 11-14: add giveaway weights, price the top three losses with your own pay, material and margin figures, and pick one to fix first.

Show actual against target on the line every hour. A crew that sees it is 80 packs behind at 10:00 can still recover before the lunch break. The page on target vs actual production tracking shows how to set the hourly target.

Choosing how to measure the line

The options differ in how much the plant learns per hour of effort. Software prices vary by vendor and scope, so the table gives cost drivers, not list prices.

OptionCost driverFitsWeak spot
Paper sheet and shift reportAbout 15 minutes of team leader time a shift: GBP 4.07 at the GBP 16.29 rateOne line, first month, agreeing codesShort stops, slow running and hourly gaps stay invisible
Packer counter and a spreadsheetEngineer days to read the signal; ask your integrator for a day rateOne or two lines with an engineer on siteBreaks when the engineer moves on
OEE software or light MES from machine signalsAsk the vendor for a price per line per monthSeveral lines, live shift numbers, losses in moneyNeeds crew cards and stop codes agreed first
Full MES with recipe and batch recordsA plant project with integration work; quote per sitePlants that need electronic records across prep and assemblyLong rollout before the line sees a gain

The third option suits a plant with more than one line. OEE software reads the packer's cycle signal, takes stop reasons from the line, and shows availability, performance and quality by shift without anyone typing up a sheet.

What you see: a shift timeline, unclassified time waiting for a reason, and the operator's line-down screen, on sample lines. Book a demo.
Plays from YouTube. Google may set cookies when you press play. Privacy policy.

For a comparison of tools by plant type, see OEE software for food and beverage. If recipes, prep rooms and allergen records belong in scope too, read about MES for food manufacturing, or a light MES for a smaller first step.

Who should pick which

Start on paper if the line has no readable packer signal yet and the first job is agreeing what a stop is.

Move to software once two or more lines run, or once changeovers and giveaway cost more per month than a line subscription. Choose a full MES when a customer, auditor or group policy requires electronic records across prep and assembly.

Questions to ask a vendor

  1. Where does the count come from on a line where people work the stations and only the packer has a signal?
  2. Can a rated speed be set per SKU, and can a short crew be logged as its own loss?
  3. Can recipe changes and allergen cleans be timed against separate standards?
  4. Can scheduled crew breaks be set as planned stops so they stay out of availability?
  5. How are rejects and QC pulls entered: a reject signal from the line, or a count by hand?
  6. Can losses be priced with each product's selling price and margin?
  7. Is the quote per line, per machine or per plant, and what does it include?

Where Fabrico fits

Fabrico is made by the publisher of this article. It is OEE software and a light MES with computer vision. The parts that matter for a sandwich line:

  • OEE by line and shift from the core machine, the packer, connected through the line PLC or a Fabrico IoT device with sensors.
  • Where a station has no usable signal, the camera add-on counts output, for example at the end of the assembly belt.
  • Stop reasons chosen by the operator at the machine in a few taps, planned and unplanned stops kept apart, so crew breaks stay out of the loss.
  • Changeovers tracked against a standard time, and scrap recorded by product and reason.
  • A line screen with actual against target hour by hour, and a TV status screen for the room.
  • With the selling price and margin of each product entered, losses are priced in money and stops are ranked by financial impact.

See the OEE, MES and computer vision features, or how a quote per plant is built on the pricing page.

Sources, accessed 26.11.2026: HSE, Assessment of repetitive tasks of the upper limbs (the ART tool); Food Standards Agency, Allergen guidance for food businesses; legislation.gov.uk, Regulation (EU) No 1169/2011, Article 24; McLauchlin et al., Listeriosis associated with pre-prepared sandwich consumption in hospital in England, 2017, Epidemiology and Infection 149, e220, 2021; GOV.UK, Food hygiene for businesses: chilling and freezing; AHDB, UK wholesale prices (dairy); ONS, RPI average price: cheese, cheddar type, per kg (CZNW); GOV.UK, National Minimum Wage and National Living Wage rates; HMRC, Rates and thresholds for employers 2026 to 2027; GOV.UK, Workplace pensions: what you, your employer and the government pay; The Pensions Regulator, Earnings thresholds; GOV.UK, Holiday entitlement.

Frequently asked questions

What is a good OEE for a sandwich production line?

There is no neutral, published benchmark for sandwich assembly lines. Compare the line with itself, week by week, under fixed rules for crew cards, count points and changeovers. The worked example on this page runs at 66.6%.

Should rated speed change when the crew is short?

No. Keep the rated speed from the crew card at standard crew and book the minutes run with fewer people under a short-crew code. Rescaling the rate hides absence from the people who plan labour.

Do crew breaks count as downtime in OEE?

Scheduled breaks are planned time and stay out of availability. A break that overruns, or a late restart after it, is an availability loss with its own stop code.

Is an allergen clean a changeover or planned downtime?

Count it as a changeover, an availability loss, timed against its own standard. Never shorten the validated clean to improve OEE; reduce the number of cleans by sequencing SKUs by allergen.

How do I measure giveaway on a hand-filled sandwich line?

Check-weigh filled bases against the recipe weight at the start, middle and end of each run, by station. Price the extra grams at the ingredient buy price and report them next to the quality rate.

How is OEE different from packs per person-hour?

OEE measures how well the line used its planned minutes. Packs per person-hour measures output against the crew hours paid. On a hand-assembly line, report both.

See which sandwich line loss costs the most. The demo shows OEE by line and shift from the core machine, stop reasons chosen by operators, actual against target hour by hour, and losses ranked by financial impact.

Book a demo

Track OEE and downtime in real time
See where lines lose time
Book a live demo.
See where lines lose time
See where lines lose time

Real Fabrico tiles, sample data.

By clicking the Accept button, you are giving your consent to the use of cookies when accessing this website and utilizing our services. To learn more about how cookies are used and managed, please refer to our Privacy Policy and Cookies Declaration