Auto Supplier Plant Closures Tracker: Bank Builds, PPAP and Run at Rate

Auto Supplier Plant Closures Tracker: Bank Builds, PPAP and Run at Rate

Automotive supplier plant closures each month from state WARN notices, and the bank build, PPAP, run at rate and OEE that moving the work demands.
Auto Supplier Plant Closures Tracker: Bank Builds, PPAP and Run at Rate

In short: When an automotive supplier plant closes, the parts it makes still have to ship. This tracker logs supplier closures from state WARN notices and company releases, and sets out what each one starts for customers and sister plants: a bank of parts built ahead of the move, the customer's approval of the new location, a run at rate at the receiving plant, and the OEE that plant needs to hold the volume.

  • Filed September to November 2026: ZF Active Safety & Electronics in Lafayette, Indiana (133 employees, staged to 2 April 2027), Dexter Axle's Plant 61 in Elkhart, Indiana (51, all on 31 December 2026) and IAC in Cottondale, Alabama (83, planned start 31 December 2026). Schaeffler announced five European site closures on 3 November 2026.
  • US closures surface on state lists because under the WARN Act an employer may not order a plant closing until 60 days after written notice. One Tier 1's supplier bulletin requires every tool move plan to include a production bank, and an approved PPAP before parts ship from the new site.
  • Example plant: a four-week bank for a moulded part costs US$29,819 to US$30,629 in overtime and interest at 72% OEE, and US$17,719 to US$18,196 at 80%.

Tracker, updated 16 November 2026. Next update: December 2026. Sources are listed at the end.

A closure notice is written for employees and the state. Read from a customer's desk, or from the sister plant that inherits the work, it is also a production schedule. The day the last crew leaves is the last day a part can be made there. Everything the customer needs after that day has to be built in advance or made somewhere else, at a rate the customer has approved. That is the same discipline that sits behind OEE for automotive Tier 1 suppliers: good parts per hour against takt, with the losses known by machine and shift. This page logs supplier closures month by month, newest first, reads each notice for what it means on the floor, and prices the bank build for an Example plant.

Supplier closures filed, September to November 2026

Each row was read on 16 November 2026 on the state's WARN list, the notice letter itself or the company's release. Dates are labelled by what they are: a letter date, a state record date or a release date.

DateCompany and siteWhat the notice saysPeopleTimingFirst question for a customer or receiving plant
3 Nov 2026 (release)Schaeffler AG: Dortmund, Morbach, Berlin and Schwalbach in Germany, Herstal in BelgiumNet 3,460 positions to go across 16 European locations, about half of them in production; five sites to closeDortmund 430, Morbach 160, Berlin about 270, Herstal about 15Mainly in 2027 and 2028On what date does each site make its last part for you?
2 Nov 2026 (state's initial report date)International Automotive Components Group North America, Cottondale, AlabamaClosure83Planned starting date 31 Dec 2026Which plant takes the work, and when does it need its first parts from you?
29 Oct 2026 (letter date)Dexter Axle LLC, Plant 61, Elkhart, Indiana (a DexKo Global company)The entire facility to close permanently51Every listed separation on 31 Dec 2026With every role leaving on one day, who pulls and ships the tools?
24 Sep 2026 (letter date; Indiana's notice date 30 Sep)ZF Active Safety & Electronics U.S. LLC, Lafayette, IndianaManufacturing operations to close permanently; the R&D centre at the same address and its 135 employees stay133First separation subject to WARN on 30 Nov 2026; schedule to 2 Apr 2027Which builds must finish before the 46 separations in the period beginning 28 Feb 2027?

Sources: Schaeffler's release, the Alabama Department of Workforce WARN list, and the letters filed with the Indiana Department of Workforce Development by Dexter Axle and ZF.

Reported, not yet in the table. WYSO reported on 11 November 2026 that Faurecia Clean Mobility plans to close its plant in Franklin, Ohio, in 2027. The Ohio Department of Job and Family Services pages could not be opened for this update, so the row waits until the notice can be read on the state's own page.

The closures sit in a shrinking workforce. The BLS counted 513,900 jobs in motor vehicle parts manufacturing in September 2026 (preliminary), 9,100 fewer than in September 2025, a fall of 1.7% (our arithmetic). Over the same year, average hourly earnings of production and nonsupervisory employees in the industry rose from US$30.67 to US$32.89 (preliminary), which matters for any bank built on overtime.

Track OEE and downtime in real time
Book a demo

Two clocks: the closure notice and the parts

Every closure in the table runs on two timetables. One is legal and public: when the people go. The other is commercial and private: when the last good part leaves the old site and the first approved part leaves the new one. The gap between them is what a bank of parts has to cover.

The notice clock

In the US, the Worker Adjustment and Retraining Notification (WARN) Act sets the first clock. Under 29 U.S. Code § 2102, an employer "shall not order a plant closing or mass layoff" until 60 days after it serves written notice. The notice goes to the employees or their representatives, to the state's rapid response unit and to the chief elected official of the local government. That second recipient is why a state's list is the first public record this tracker reads.

The definitions in 29 U.S. Code § 2101 set who must file. An employer is a business with 100 or more employees, excluding part-time employees, or with 100 or more employees who together work at least 4,000 hours a week, not counting overtime. A plant closing is the shutdown of a single site that causes an employment loss for 50 or more employees, excluding part-time employees, in any 30-day period. Two things follow for anyone using a tracker like this one:

  • Small closures may never appear. A site closure that costs fewer than 50 jobs falls below the plant-closing threshold, and an employer with fewer than 100 employees is outside the definition, so either may never reach a state list. Dexter Axle's Plant 61, at 51 employees, is one above the threshold.
  • Sixty days can be shortened. Section 2102(b) lets the period be shortened for a faltering company seeking capital, for business circumstances that were not reasonably foreseeable, and drops it for a natural disaster. A customer cannot count on two months.

States publish what they receive in different shapes. Alabama's list gives an initial report date and a planned starting date. Indiana posts the letters themselves, and some letters carry a full run-down schedule by job title, which tells a customer more than a headcount does. For Europe, this tracker found no public list of this kind: Schaeffler announced its plan in a release and will carry it out "in close dialogue with employee representatives and works councils", with the measures scheduled primarily for 2027 and 2028. In that case the closures were public long before most of the work is due, the reverse of a 60-day US notice.

The bank covers the moveExample plant: 6,300 parts a week25,200 partsbuilduseweek 0week 812Weeks 1 to 8build 25,200 partsWeek 9pull the tool, ship itWeek 10install and trialWeeks 11, 12PPAP, run at rate, approval60 daysWARN noticebefore closingBankin every toolmove planPPAPapproved beforeparts shipBank first, while the crew stays.Approve the new site in time.
Example plant data: a 25,200-part bank built over eight weeks, then used while the tool moves and the new site is approved. The bank and approval steps follow Lear's supplier bulletin; sources are listed at the end.

The parts clock

The customer's rules set the second clock, and they are written into supplier manuals. Two documents from buyers of parts show the pattern: a Tier 1's bulletin to its suppliers and a component maker's PPAP handbook.

  1. A bank of parts. Lear's supplier bulletin on production tool transfer moves says "Any Tool Move Plan must include a production bank" to protect its production and service requirements, and that all shared tooling must be identified in the plan.
  2. Approval of the new location. The same bulletin requires advance written approval for all production location changes, and an approved PPAP, Level 3 unless otherwise directed, before production material ships from the new location. An exit PPAP from the old facility may be required too, and the supplier carries "any and all costs" of the change. Prestolite Electric's supplier PPAP handbook lists "Tooling, production, or equipment transferred to a different site" among its reasons to ask for a PPAP submission.
  3. A run at the standard rate. The Prestolite handbook defines a significant production run as at least 300 consecutive parts made with production equipment, tooling and people at the standard production rate, with parts measured from each unique process, down to each cavity of a multi-cavity tool. A tool moved onto a different press is a new process to prove, which is what a run at rate tests.
  4. Capacity at the receiving line. Once approved, the receiving press has to make the customer's weekly demand and rebuild its own stock, with whatever OEE it really holds. The mechanics of shifting equipment and climbing back to a baseline are covered in the guide to moving a production line; this page deals with what the customer needs while that happens.

The bank is the bridge between the two clocks. It is built while the old crew is still there and drawn down while the tool travels, is installed and is approved. Its size is the gap plus a margin; its cost depends on how many spare hours the sending cell really has.

Case notes, November 2026

Each note uses facts from the notice itself. Where we read more into a notice than it says, the text marks it as our reading.

ZF Active Safety & Electronics, Lafayette, Indiana (letter dated 24 September 2026)

ZF's letter to Indiana says the company will permanently close the manufacturing operations at 800 Heath Street, Lafayette, with 133 affected employees and the first separation subject to WARN on 30 November 2026. The R&D centre at the same address and its 135 employees are not affected. The letter attaches a projected schedule; each row gives the date its period begins.

Period beginningSeparationsRunning totalRoles named in the schedule include
5 Nov 202611Assembler
20 Nov 202645Production technicians, layout and QC inspectors
30 Nov 2026510Production technicians and operators
5 Jan 2027717Production technicians, an operator, materials
1, 8 and 15 Feb 20272744Production technicians
28 Feb 2027469036 assemblers, 2 G assemblers, inspectors, materials
5 Mar 2027321222 toolmakers, 4 machine repairers, 2 electricians, supervisors, engineers, a supplier quality engineer
12 Mar 20277129Schedulers, payroll, supervisors, engineers
2 Apr 20274133Plant manager and three other managers

Source: our count of the schedule attached to ZF's letter. The letter does not say what the plant makes or where the work goes.

  • The last full-crew builds come before 28 February 2027. By the end of that period 90 of the 133 have gone, 36 assemblers in that period alone. Our reading: any bank a customer needs from Lafayette has to be complete before that step, not planned for March.
  • The trades leave in the next period, five days later. Toolmakers, machine repairers and electricians are scheduled for the period beginning 5 March 2027. Our reading: that is the week to pull tools and machines, while the people who know them are still on site. A receiving plant should book its riggers and its own maintenance crew for those dates.
  • Engineering stays; the floor's knowledge goes. With the R&D centre's 135 people unaffected, product engineering remains in Lafayette, but the settings, stop fixes and scrap causes held by the production crew leave between November and February. Ask for them per part before 28 February.

Dexter Axle, Plant 61, Elkhart, Indiana (letter dated 29 October 2026)

Dexter Axle's letter says the entire facility at 21608 Protecta Drive is expected to close permanently, with completion targeted for 31 December 2026, the same date as the first separation. The closing affects 51 employees, none represented by a union. Exhibit A lists every job title, from assemblers and welders to the maintenance manager, the quality manager and the plant manager, with the same date: 31 December 2026. Indiana's list files the company under motor vehicle transmission and power train parts manufacturing.

  • One date for everyone. Unlike Lafayette, the exhibit schedules nobody to stay past 31 December to pull tools or answer questions. From the letter to the closing date is 63 days (our arithmetic), across the Thanksgiving and year-end holidays. Tool moves and the handover of records have to fit inside that window or be staffed from another site.
  • Welded and assembled parts are the work that moves. Assemblers in three grades and welders in two are the largest groups in Exhibit A. A weld cell rebuilt at another site is a new process in the sense of the Prestolite handbook, so the approval run belongs in the plan from day one.
  • The receiving site is not named. The letter is sent from Dexter's address at 2900 Industrial Parkway East, Elkhart, a different address from the closing plant, but it does not say where Plant 61's work goes. A customer's first written question is which site, because the approval run cannot be booked until the cell is named.

IAC, Cottondale, Alabama (state initial report date 2 November 2026)

The Alabama Department of Workforce WARN list records a closing at International Automotive Components Group North America in Cottondale, with 83 affected employees, an initial report date of 2 November 2026 and a planned starting date of 31 December 2026. The list does not give the date of the company's own letter. In October 2020 the Alabama Department of Commerce announced US$34.3 million of new capital and 119 new jobs at the Cottondale plant, which it said makes door panels and overhead systems for vehicle makers.

  • Fifty-nine days between the state's two dates (our arithmetic). For a sub-supplier shipping into Cottondale, the last ship date there and the first ship date to whichever plant takes the work fall in the same weeks as the year-end holidays. Confirm both dates in writing now.
  • A change of ship-to is still a change. If your parts go into the door panels or overhead systems, the receiving plant and its customer decide what they need from you. Ask which approvals, which labels and which quantities, before your own bank is built to the old plan.
  • Six years from expansion to closure. Six years separate the 2020 investment and the closure notice. Keep a register of the tools you run for each customer plant and who owns them, so a closure notice starts a plan rather than a search.

Schaeffler, five European sites (release dated 3 November 2026)

Schaeffler plans a net reduction of 3,460 positions in Europe, about 2,660 of them in Germany, affecting 16 locations. About 50% of the affected positions are in production and 30% in research and development. Five sites close: Dortmund (430 people) and Morbach (160), both in the Powertrain & Chassis division, Berlin (about 270) and Schwalbach in Germany, and Herstal in Belgium (about 15). For Berlin and Schwalbach, the release says "a large portion of these approximately 385 employees" is expected to transfer to another Schaeffler site in Germany. Toolmaking at Höchstadt is to be discontinued. The release names weakened demand for combustion engine vehicles, a delayed ramp-up of electric mobility and above-average costs per employee in Germany, and puts the measures mainly in 2027 and 2028.

  • A two-year window, not 60 days. A supplier to Dortmund or Morbach has time to plan its bank and approvals, provided it asks now for each site's last build date. The risk is the opposite of the US cases: a plan that drifts because the date feels far away.
  • Some work moves with people, some does not. A large portion of the Berlin and Schwalbach staff is expected to move to another Schaeffler site; the release states no such transfer for Dortmund, Morbach or Herstal. Our reading: parts from the first two sites may keep their teams at a new address, while parts from the other three need a receiving team that has not made them before.
  • An in-house toolroom stops. With toolmaking at Höchstadt to end, tool repair for the affected work will come from somewhere else. A repair lead time is part of the bank: size it for a tool fault at the new site, not only for the move.

The next update adds new cases under these, each with its date and what the date is.

Worked example: pricing a four-week bank for a moulded part

Example plant. Every operating figure in this section is Example data; the unit value, the interest rate and the wage are sourced. The sums are not an estimate for any company named above.

  • The part: a moulded body part, classed under HS 8708.29 ("Vehicles; parts and accessories, of bodies, other than safety seat belts", as UN Comtrade names it), weighing 0.35 kg. The Tier 1 customer takes 6,300 a week.
  • The sending cell, at the closing plant: a two-cavity tool on one press with a 57.6-second cycle, so 125 parts an hour at the ideal rate. Two 8-hour shifts on five days give 80 hours a week. At 72% OEE that is 125 x 0.72 = 90 good parts an hour and 80 x 90 = 7,200 a week, 900 above demand.
  • Crew and overtime: three people per shift, each already on 40 hours a week. The cell can add two 8-hour shifts on Saturday and on Sunday, 32 press hours a weekend.
  • The gap: week 1, pull the tool and ship it; week 2, install and trial at the sister plant; weeks 3 and 4, the PPAP run, the run at rate and the customer's approval. Nothing ships from the new site before approval, so the bank is 4 x 6,300 = 25,200 parts.
  • The window: 8 weeks from the decision to the tool pull, a little shorter than the WARN notice period.

Step 1: what regular time builds. 8 weeks x 900 = 7,200 parts. That leaves 25,200 minus 7,200 = 18,000 parts for the weekends.

Step 2: weekend press hours. 18,000 / 90 = 200 press hours, 25 of the 32 weekend shifts available over 8 weekends. With three people per shift that is 200 x 3 = 600 crew hours.

Step 3: what the overtime costs. The US Department of Labor's overtime rule requires covered, non-exempt employees to be paid at least time and one-half for hours over 40 in a workweek. Every weekend hour here is over 40. At the BLS earnings for motor vehicle parts manufacturing, US$32.01 in August 2026 and US$32.89 in September 2026 (preliminary): 600 x 1.5 x 32.01 = US$28,809.00 and 600 x 1.5 x 32.89 = US$29,601.00. These are earnings, before benefits and any premium in a labour contract, so the money is a floor.

Step 4: the cash held in the bank. UN Comtrade records 2025 US imports of HS 8708.29 from Canada at US$4,562,750,189 (FOB) for 322,043,423.718 kg, and from Mexico at US$7,826,033,162 (FOB) for 542,118,642.89 kg, weights Comtrade marks as estimated. That is US$14.17 and US$14.44 a kg (our arithmetic), an average across body parts rather than a price for any one part. At 0.35 kg: 0.35 x 14.17 = US$4.96 and 0.35 x 14.44 = US$5.05 a part, rounded. At its peak the bank holds 25,200 x 4.96 = US$124,992 to 25,200 x 5.05 = US$127,260.

Step 5: the carrying cost. The Federal Reserve's bank prime loan rate (H.15, via FRED) was 7.00% on 9 November 2026. The bank builds for 8 weeks and is used up over 4, so on average about half the peak is held for 12 weeks (a simplification). Interest: 62,496 x 0.07 x 12 / 52 = US$1,009.55 and 63,630 x 0.07 x 12 / 52 = US$1,027.87. This is interest only; the wider inventory carrying cost adds storage, handling and risk, which this example does not price.

Step 6: the bank at 72% OEE. US$28,809.00 + US$1,009.55 = US$29,818.55 to US$29,601.00 + US$1,027.87 = US$30,628.87.

Step 7: the same bank at 80% OEE. 125 x 0.80 = 100 good parts an hour and 8,000 a week, 1,700 above demand. 8 x 1,700 = 13,600 parts on regular time, leaving 25,200 minus 13,600 = 11,600. 11,600 / 100 = 116 press hours, or 348 crew hours: 348 x 1.5 x 32.01 = US$16,709.22 and 348 x 1.5 x 32.89 = US$17,168.58. With the same interest the bank costs US$17,718.77 to US$18,196.45. The 252 crew hours saved are worth 252 x 1.5 x 32.01 = US$12,099.78 to 252 x 1.5 x 32.89 = US$12,432.42.

Step 8: plan for a two-week approval slip. If the receiving plant's PPAP could come back with an open point, the bank needs 2 x 6,300 = 12,600 more parts, and they have to be built before the tool leaves. At 72%: 12,600 / 90 = 140 more press hours, 340 in all, against 8 x 32 = 256 weekend hours available. The cell is 84 hours short, or 84 x 90 = 7,560 parts, 1.2 weeks of the customer's demand. At 80%: 12,600 / 100 = 126 more hours, 242 in all, inside the 256.

Weekend hours to build the bankExample plant, 8 weekends, 256 hours available72% OEE, plan: 200 h72% OEE, 2-week slip: 340 h (84 h short)80% OEE, plan: 116 h80% OEE, 2-week slip: 242 hDashed line: 256 weekend hours. 84 h short = 7,560 parts.
Example data. Weekend press hours a cell needs to build a four-week bank in eight weeks at two OEE levels, with and without a two-week approval slip.

The overtime is the visible cost. The real exposure is the slip: at 72% the window cannot absorb two weeks of delay at the receiving plant, and at 80% it can, with 14 hours to spare. The same arithmetic applies to any cell that is asked for a bank; the trade-off between extra shifts and recovered hours is set out in overtime vs OEE.

Book a demo and see OEE per line and shift.

Bank, bridge tool or staged move: choosing how to cover the gap

The bank is one answer. The table puts it next to the others, with the anchors from the cases and the worked example.

OptionChoose it ifCost anchor on this pageWatch for
Build the bank on weekend overtime at the closing plantThe crew stays until the tool pull and the cell has weekend hours freeUS$28,809 to US$29,601 of overtime for 25,200 parts at 72% OEE (Example)A two-week approval slip outruns the weekend hours
Lift OEE first, then build the bankThere are weeks between the notice and the build, and the cell's top losses are known116 instead of 200 weekend press hours at 80% OEE (Example)The gain has to show in the counts before the bank plan relies on it
Start the bank early, on a long noticeThe closure date is known long in advance, as with Schaeffler's measures planned mainly for 2027 and 2028Cash: US$124,992 to US$127,260 at the peak; interest US$1,010 to US$1,028Engineering changes made after parts are built; parts aging in stock
Bridge tool or second press at the receiving plantThe part's volume or risk justifies a second tool, so nothing stops while the first travelsA toolmaker's quote (not priced here)Two processes to approve: parts from each unique process
Move in stages, one tool at a timeSeveral part numbers share a press, a crew or a customerA smaller bank per tool, built in turnShared tooling has to be named in the tool move plan

Questions to ask the customer's buyer and supplier quality engineer before a tool moves:

  • Which approval does the new location need, and at what PPAP level?
  • Will an exit PPAP from the closing plant be required?
  • How many weeks of bank do you want, and does it include service parts?
  • Which tools are shared with other parts or customers?
  • What run at rate will you witness at the receiving plant: how long, on which shift, and does it include a changeover?
  • Who pays for the move, the bank and any premium freight if the bank runs short?

Who owns which date

A closure fails on the dates nobody owned. Give each one a name and a record that proves it.

RoleThe date they ownThe record that proves it
Plant manager, closing plantLast build date for each partWeekly output against the bank target
Production manager, closing plantThe weekend shifts that build the bankGood parts and OEE per shift
Maintenance and toolroomTool pull, repair and installationLast shots, tool condition, stop history by machine
Supplier quality engineerPPAP submission and approval for the new siteThe significant production run: count, rate, each cavity
Plant manager, receiving plantFirst approved shipment, and the run at rateGood parts per hour against the quoted rate, by shift
Materials and logisticsThe day the bank runs outParts in stock against weeks of demand, each week

The first 30 days after a closure notice

Whether the notice is your own plant's or a customer's, the first month decides whether the bank is a plan or a scramble.

This week

  1. List every part made at, or shipped to, the closing site, with weekly demand and the tool and press it runs on.
  2. Read the notice for the last build date. A staged schedule like ZF's gives it by role; a single-date closure like Dexter's gives one day for everything.
  3. Ask the customer in writing which approvals the new location needs and how big a bank it expects.

By day 30

  1. Measure OEE by shift on each sending cell for two weeks, so the bank plan uses the rate the cell really holds.
  2. Size each bank from the gap plan plus a slip margin, and test it against the weekend hours available, as in the worked example.
  3. Copy settings, stop reasons and scrap causes per part to the receiving plant before the crew that knows them leaves. The same records bound the population if a part built before the move is recalled later, as the automotive supplier recalls tracker shows.
  4. Book the receiving plant's run at rate with its own crew, on a normal shift, with a changeover in it.
  5. Track the bank every week: parts built against target, and weeks of demand covered.

The record that should move with the tool

A tool travels in a truck; its history travels in a file. On its first day the receiving plant needs the sending cell's good parts per hour, its stops by reason and its scrap causes, by shift, for every part it takes over. With that, its first weeks have a target and a list of known faults. When a supplier files for insolvency instead of closing, the customer's waiting minutes, tool ownership checks and resourcing choice are set out in the supplier insolvencies tracker. The same record sizes the bank before the move, because the hours a cell can give above demand depend on the OEE it really runs at, not on its nameplate. For a press shop, OEE for injection moulding shows which losses to watch; for the traceability and routings that a move also touches, see MES for automotive suppliers.

Fabrico is a cloud OEE and light MES platform. It shows OEE and losses by machine, line and shift, with data from the machine's PLC or an IoT device with sensors on the machines you connect, and operators give the reason for a stop at the machine. With the selling price and margin of each SKU entered, losses are priced in money, so stops can be ranked by what they cost. On manual stations, AI cameras (an add-on) count output. The building blocks are OEE software, a light MES for the production record, and computer vision for manual stations.

Book a demo and see downtime by machine and shift.

What people ask next

What is a bank build when a supplier plant closes?

Parts built ahead of a tool or production move, to cover the weeks when nothing can ship from the old site or the new one. Lear's supplier bulletin requires every tool move plan to include a production bank. Size it from the gap: the tool pull, the installation and the approval run at the new site, plus a margin for a slip. In the Example plant on this page, four weeks of demand is 25,200 parts.

Does moving production to another plant need a new PPAP?

The customer decides, and supplier manuals name a site change as a trigger. Prestolite Electric's PPAP handbook lists tooling, production or equipment transferred to a different site among its reasons to ask for a submission. Lear requires advance written approval for all production location changes and an approved PPAP, Level 3 unless otherwise directed, before parts ship from the new location. Ask the customer in writing which approval it needs.

How much notice does a US plant closure need?

Under the WARN Act, 29 U.S. Code 2102, a covered employer, broadly one with 100 or more employees not counting part-time staff, may not order a plant closing until 60 days after written notice to the employees or their representatives, the state's rapid response unit and the local chief elected official. A plant closing means an employment loss for 50 or more employees, excluding part-time employees, at one site in any 30-day period. The period can be shortened for a faltering company or unforeseeable business circumstances, and no notice is needed after a natural disaster.

How many weeks of bank should a supplier build?

None of the sources on this page sets a number. Build the plan from the gap: the weeks to pull, ship and install the tool, plus the PPAP run, the run at rate and the customer's approval, then add a margin and test it against the hours the sending cell has free. In the Example plant, a two-week approval slip made the plan fail at 72% OEE and still fit at 80%.

Where can I find automotive supplier plant closures?

On state WARN lists for US closures: Alabama's Department of Workforce lists dates and headcounts, and Indiana's Department of Workforce Development posts the notice letters, some with a schedule by job title. European closures appear in company releases. This tracker reads both and is updated monthly.

How does OEE affect a bank build?

The bank comes from the hours a cell has above demand, and those hours depend on the OEE the cell really holds. In the Example plant, a four-week bank needs 200 weekend press hours at 72% OEE and 116 at 80%, which is US$28,809 to US$29,601 of overtime against US$16,709 to US$17,169.

Sources

Sources accessed on 16 November 2026 unless marked as accessed on another date. Dates are publication dates where a page gives one; other dates are labelled as what they are.

Track OEE and downtime in real time
See where lines lose time
Book a live demo.
See where lines lose time
See where lines lose time

Real Fabrico tiles, sample data.

By clicking the Accept button, you are giving your consent to the use of cookies when accessing this website and utilizing our services. To learn more about how cookies are used and managed, please refer to our Privacy Policy and Cookies Declaration