Supplier Insolvencies Tracker: Auto Supplier Cases and What the Customer Measures
In short: A German supplier that files for insolvency does not stop shipping on the day it files. Where the court appoints a provisional administrator with power over the assets, that administrator has to continue the business until the court decides on opening proceedings, and Insolvenzgeld pays employees' wages for the three months before the insolvency event. Those weeks are the customer's decision window: support the supplier, buy ahead, move the parts or buy the business. This tracker logs automotive supplier cases each month, and what the customer's line can measure meanwhile.
- German courts registered 2,067 company insolvency filings in August 2026, 4.4% more than a year earlier, and 17,252 from January to August (Destatis, 13 November 2026).
- Cases: KARL KLINK Räumtechnik (10 November 2026), Weber Magdeburg (16 October 2026), Bohai Automotive and the Schlote plants (28 September 2026).
- Example plant: 805 minutes of waiting for one supplier's housings in four weeks cost 644 calipers and EUR 4,308.75 to 12,037.13 of margin. An eight-week last-time buy ties up EUR 907,200 and costs EUR 1,849.29 to 2,721.60 in interest.
Tracker, updated 18 November 2026. Next update: December 2026, with the cases released since. Sources are listed at the end.
When a Tier 2 goes insolvent, the Tier 1's line feels it before any court decision does: deliveries arrive late or short, and the line waits. The decision to keep the supplier alive needs two numbers no insolvency notice contains: how reliable the supplier's deliveries are now, and what the waiting costs on the customer's assembly line. Both come from the production record behind OEE for automotive Tier 1 suppliers, with the losses kept by line, shift and reason, and from the plant's MES for automotive suppliers, where a stop is recorded with the product that was running. This page logs the cases, explains the German procedure in the order it runs, and prices one supplier's waiting minutes against a last-time buy for an Example plant.
Supplier insolvencies, case by case
Each row comes from the administrator's own release or the company's own statement, with the release date. Court notices are published on the federal portal for insolvency announcements; the rows below use the administrators' releases because they state what happens to the business.
| Release date | Company | What it makes | Court and administrator | Status in the release |
|---|---|---|---|---|
| 10 November 2026 | KARL KLINK Räumtechnik GmbH, Niefern-Öschelbronn | Broaching machines and tools, contract broaching, tool sharpening; about 100 staff | Court not stated; provisional administrators Holger Blümle and Dr. Markus Schuster, Schultze & Braun | Provisional proceedings; orders produced as planned; wages secured to the end of the year |
| 16 October 2026 | Weber Magdeburg GmbH, Magdeburg (Albert Weber group, Markdorf) | Cylinder heads, for about 25 years; about 120 staff | Amtsgericht Konstanz; provisional administrator Dr. Jan Markus Plathner, Brinkmann & Partner, appointed 14 October 2026 | Filing made; pre-financing of Insolvenzgeld being examined |
| 28 September 2026 | Bohai Automotive GmbH and three sister companies, Harzgerode | Not named in the release; about 550 staff | Amtsgericht Halle (Saale), filing April 2025; administrator Olaf Spiekermann | Operations cease on 31 January 2027; the main customers had paid several million euros to keep production going |
| 28 September 2026 | Schlote Harzgerode GmbH and Getriebe- und Antriebstechnik Wernigerode GmbH | Supplier to Bohai on the same site; about 180 staff at both sites | Amtsgericht Hildesheim, filing 2025; administrator Manuel Sack | Production ends on 31 January 2027; customers had absorbed losses in the double-digit millions |
Sources: the releases linked in each case below. "Release date" is the date printed on the release; filing dates are given only where the release states them.
Three rules for reading the table:
- A filing is not a closure. KARL KLINK's release says orders are produced as planned under provisional administrators, and Weber Magdeburg's release reports a filing, not a shutdown. Bohai and Schlote kept producing for more than a year after filing, and close only because no buyer and no new business were found.
- The release states what the court notice does not. A court notice names the court, the case and the administrator. Whether orders are still produced, and for how long wages are secured, is in the administrator's release.
- The customer appears in the record. In both closing cases the releases name the money customers paid while production went on. That is the decision this page is about.
How a German insolvency keeps the supplier shipping
The Insolvency Code (Insolvenzordnung, InsO) and the Social Code III (SGB III) set the order of events. The English below is a working translation, not an official one; the linked German texts govern.
| Step, in time order | Rule | What it means for the customer |
|---|---|---|
| 1. Filing and provisional measures | InsO § 21: the court orders the measures needed to prevent a detrimental change in the debtor's assets before it decides on the filing. It may appoint a provisional administrator and impose a general prohibition on disposal, or make the debtor's dispositions subject to the administrator's consent. | From this point, contract changes, price talks and tool questions go to the provisional administrator as well as to the supplier's management. |
| 2. The business continues | InsO § 22: where a general prohibition on disposal is imposed, the provisional administrator has to continue the debtor's business until the court decides on opening, unless the court agrees to a shutdown to avoid a considerable reduction of the assets. | Deliveries go on, but the administrator now weighs each order against the estate. Reliability can change week by week. |
| 3. Wages for three months | SGB III § 165: employees receive Insolvenzgeld for the three months of the employment relationship preceding the insolvency event. The events are the opening of proceedings, the rejection of the filing for lack of assets, or the complete end of business activity in Germany under further conditions. | In those months the Federal Employment Agency, not the estate, carries the wages it covers, while a buyer or a customer deal is sought. |
| 4. Opening | InsO § 103: for a mutual contract that neither side has fully performed when proceedings open, the administrator may perform it in place of the debtor. If the administrator refuses, the other party's claim is only an insolvency claim. Asked by the other party, the administrator has to declare the choice without delay ("unverzüglich"). | Open delivery contracts and open purchase obligations are confirmed or refused here. Ask for the declaration in writing. |
| 5. Self-administration, where ordered | InsO § 270: if the court orders self-administration (Eigenverwaltung), the debtor's management runs the estate under the supervision of a Sachwalter. | The customer keeps talking to the same managers, with a court-appointed supervisor beside them. |
| 6. Assets that are not the supplier's | InsO § 47: whoever can show that an item does not belong to the estate is not an insolvency creditor; the claim to separate it (Aussonderung) follows the law outside insolvency. | Customer-owned tools and gauges can be claimed back, if the ownership can be shown. See the tools section below. |
The Federal Employment Agency's page for employers adds three practical points: Insolvenzgeld is paid as a rule at the level of net pay, higher earners are capped, and the application is due within two months of the opening. The page also offers the form for consent to pre-financing, the route by which a bank advances the wages before the agency pays. That is the step Weber Magdeburg's release says was being examined.
Two inferences follow, both from the rules above rather than from any case. First, the three months of Insolvenzgeld and the court's decision on opening frame the window in which the supplier's costs are lowest and its future is open: the customer's decision belongs inside it. Second, the national statistic lags the same window: Destatis's release of 13 November 2026 notes that filings enter the statistic only after the court's first decision, and that the filing itself often came nearly three months earlier. The August 2026 count of 2,067 company filings is a picture of the early summer.
Cases, newest first
Each case ends with what its own release tells a customer to check. A new month's cases are added at the top, with the date of each release.
KARL KLINK Räumtechnik, release of 10 November 2026: orders produced as planned
The administrators' release of 10 November 2026 says KARL KLINK Räumtechnik GmbH of Niefern-Öschelbronn, founded in 1900, has filed for insolvency, and names Holger Blümle and Dr. Markus Schuster of Schultze & Braun as provisional administrators. The company makes broaching machines and tools, broaches parts for others as a contract manufacturer, and resharpens tools with a collection and delivery service. Its customers include the automotive industry and its suppliers, agricultural machinery and rail technology. The release states that orders are processed and produced as planned ("wie geplant"), that the October pay will be made as soon as possible and November and December on the usual dates, so wages are secured to the end of the year. It names the after-effects of an insolvency in 2025 (without saying whose), weak investment demand and higher energy costs as the causes, and says an investor solution is the likely route.
- Check the resharpening loop. A plant that sends its broaches to Niefern-Öschelbronn for sharpening depends on a collection and delivery service, not only on new tools. Count the days each broach set is away and the stops logged as "waiting for tools" on the broaching machine, from now to the end of December.
- Contract broaching is a delivery like any other. Parts broached on contract arrive by date and quantity. Track on-time in full by part number, starting with the deliveries due before the end of the year, when the wage cover the release names runs out.
- Ask about 2025 and about buyers. The release blames the after-effects of an insolvency in 2025 and says management had already held talks with interested buyers. Ask the administrators whose insolvency that was, and how far the buyer talks had gone before the filing.
Weber Magdeburg, release of 16 October 2026: the wage bridge not yet settled
The administrator's release of 16 October 2026 says Weber Magdeburg GmbH, part of the Albert Weber group based in Markdorf, has filed for insolvency, and that the Amtsgericht Konstanz appointed Dr. Jan Markus Plathner of Brinkmann & Partner as provisional administrator on 14 October 2026. The company has made cylinder heads in Magdeburg for about 25 years and employs about 120 people. The release says the pre-financing of Insolvenzgeld is being examined. It says nothing about customers or deliveries.
- Until the pre-financing is settled, nothing is settled. A release that says the wage advance is still being examined describes a business whose next weeks depend on it. A customer taking cylinder heads asks the administrator for the date the advance is agreed, and counts deliveries daily until then.
- The second source is the customer's question. Whether another maker can supply a cylinder head in time is for the customer to establish, and its record of late and short deliveries since 14 October is the evidence for the choice between support and a second source.
- The group is not the plant. The release names the Magdeburg company only. Contracts signed with another company of the group need their own check.
Bohai Automotive, release of 28 September 2026: support bought time, not a buyer
The administrator's release of 28 September 2026 says Bohai Automotive GmbH and three sister companies in Harzgerode filed in April 2025 at the Amtsgericht Halle (Saale), with Olaf Spiekermann first as provisional administrator and then as administrator. Production ran at a loss throughout and continued only because the main customers paid several million euros. An international investor process found no viable overall solution, and talks with prospects in defence and other industries brought no new orders. Orders had been falling for years, which raised unit costs. Operations cease on 31 January 2027, affecting about 550 employees.
- Price the support by the month. From the filing in April 2025 to the end of January 2027 is about 21 months of production paid for partly by customers. A customer that funds a supplier needs its own monthly figure: the support paid against the parts received and the waiting minutes avoided.
- Falling volume is the cause, not a side note. The release ties the losses to orders falling over several years and to rising unit costs. A customer whose call-offs to a supplier are falling is part of that arithmetic; the support does not change it.
- Use the time to move the parts. When the support ends without a buyer, the parts still have to come from somewhere on 1 February 2027. The months of support are the time for the second source to be approved.
Schlote plants, release of 28 September 2026: a supplier's supplier
The administrator's release of 28 September 2026 says Schlote Harzgerode GmbH and Getriebe- und Antriebstechnik Wernigerode GmbH end production on 31 January 2027. The Schlote group filed in 2025 at the Amtsgericht Hildesheim, and administrator Manuel Sack has kept the business running since. Customers absorbed losses in the double-digit millions ("in zweistelliger Millionenhöhe"). Investors and customers did not reach an agreement, despite support from the state government of Saxony-Anhalt. Schlote supplies Bohai, which sits on the same site in Harzgerode, so its production ends with Bohai's. About 180 employees work at the two sites.
- Map the supplier's own customers. Schlote closes because its customer next door closes. A buyer of parts from Wernigerode had a risk that sat one step further down the chain, in Bohai's order book.
- Two filings, one end date. Both releases of 28 September give 31 January 2027. A Tier 1 that buys from both has one deadline for two resourcings, and its approval capacity is the constraint to count.
- Loss cover is a decision to repeat each month. Double-digit millions in loss absorption is a price paid for continuity. The record that justifies continuing to pay it is the delivery record and the waiting minutes, kept every week.
Earlier cases from September 2026 are listed in the table above; a case enters the tracker only when its administrator's or company's release can be read.
Four questions the customer's line can answer
An insolvency notice answers legal questions. The customer's decision rests on four plant-floor ones, each with a number behind it.
- How reliable are the supplier's deliveries now? On-time in full by part number and by week: deliveries due, deliveries arriving complete on the due date, and parts received against parts due. A weekly trend shows whether the administrator is holding the supplier steady or rationing it.
- How many minutes did the line lose waiting for that supplier's parts? Only a stop reason gives this. "Waiting for parts" needs a second level naming the supplier and the part, entered by the operator when the line stops, as set out in downtime reason code design and in waiting for material in OEE.
- What does a last-time buy or a buffer cost against those minutes? The buffer ties up cash and costs interest; the waiting minutes cost output and margin. The two can be compared in money once both are measured, as the example below does. The general method is in safety stock and inventory carrying cost.
- Who owns the tools, under the tool loan agreement? If the parts have to move, the tools have to move with them, and only tools that can be shown to be the customer's can be separated from the estate under InsO § 47.
The second question is the one that slips. Waiting minutes caused by a supplier show up on the customer's line as starvation: the line is ready and the parts are not. Without a reason that names the supplier, they disappear into the line's availability loss. How a starved station hides inside an otherwise healthy line is explained in starvation and blocking.
Worked example: a caliper line waiting for housings
Example plant. Every operating figure in this section is Example data; the margin range, the interest rates and the legal rules are sourced. The plant and the supplier are not any company named above.
A Tier 1 assembles brake calipers on line 3, two shifts a day, five days a week, 7.5 planned hours a shift: 75 planned hours a week. The line makes 48 calipers an hour, 48 x 75 = 3,600 a week, which is also the customer's weekly call-off. The machined caliper housings come from one Tier 2, the Example supplier, in two deliveries a day, ten a week, of 360 housings each. Each housing costs EUR 31.50 and each caliper sells for EUR 118. The Example supplier files for insolvency, a provisional administrator is appointed, and deliveries continue.
Step 1: count the deliveries. For four weeks after the filing, receiving logs each delivery against its due date and quantity.
Step 2: log the waiting. When line 3 stops for want of housings, the operator gives the reason "waiting for parts: housings, Example supplier". The minutes are summed by week.
| Week after filing | Deliveries on time in full | Housings received on time | Line 3 waiting for housings | Calipers not built |
|---|---|---|---|---|
| Week 1 | 9 of 10 | 3,510 of 3,600 | 95 min | 76 |
| Week 2 | 7 of 10 | 3,240 of 3,600 | 160 min | 128 |
| Week 3 | 6 of 10 | 3,060 of 3,600 | 240 min | 192 |
| Week 4 | 5 of 10 | 2,880 of 3,600 | 310 min | 248 |
| Four weeks | 27 of 40, 67.5% | 12,690 of 14,400, 88.1% | 805 min | 644 |
Example data. Calipers not built = waiting minutes x 48 / 60 = minutes x 0.8. The 1,710 late housings cost fewer calipers than their number, because the line-side stock covered part of each gap until they arrived.
Step 3: price the waiting. 644 calipers x EUR 118 = EUR 75,992 of sales not made in four weeks. The NYU Stern margin data, updated January 2026, give the auto parts industry (35 listed United States firms) a pre-tax unadjusted operating margin of 5.67% and a gross margin of 15.84%. As a range: 75,992 x 5.67% = EUR 4,308.75 to 75,992 x 15.84% = EUR 12,037.13 of margin lost. The trend matters more than the total. Week 4 alone lost 248 calipers, EUR 29,264 of sales, EUR 1,659.27 to 4,635.42 of margin, more than three times week 1. The crew of six stood for 6 x 805 / 60 = 80.5 hours in all, which are paid and not priced here.
Step 4: price a last-time buy. A second source for the housings needs eight weeks to approval (Example data), so the buffer has to cover eight weeks: 8 x 3,600 = 28,800 housings x EUR 31.50 = EUR 907,200. Built before the bridge starts and drawn down evenly, the average stock is half of that, EUR 453,600. At the ECB's main refinancing rate of 2.65% from 16 September 2026 (key ECB interest rates), eight weeks of interest are 453,600 x 2.65% x 8 / 52 = EUR 1,849.29. At the euro area composite cost of borrowing for new loans to corporations, 3.90% in September 2026 (ECB release of 2 November 2026), they are 453,600 x 3.90% x 8 / 52 = EUR 2,721.60. Storage, handling and the risk of housings left over at a change of part are not priced.
Step 5: price the alternative. If week 4's waiting continues for the eight weeks of the bridge: 8 x 310 = 2,480 minutes, 2,480 x 0.8 = 1,984 calipers, 1,984 x 118 = EUR 234,112 of sales, and EUR 13,274.15 to 37,083.34 of margin at the same range.
| Eight-week bridge | Wait it out (week 4 rate) | Last-time buy of 28,800 housings |
|---|---|---|
| Calipers not built | 1,984 | 0, if the buy is delivered |
| Margin lost, at 5.67% to 15.84% | EUR 13,274.15 to 37,083.34 | None counted |
| Cash tied up at the start | None | EUR 907,200 |
| Interest, at 2.65% to 3.90% | None | EUR 1,849.29 to 2,721.60 |
| What it depends on | The supplier getting no worse than week 4 | The supplier building 28,800 extra housings while it ships 2,880 of 3,600 a week |
Step 6: read the result. On paper the buffer wins by a wide margin: no more than EUR 2,721.60 of interest against at least EUR 13,274.15 of lost margin. The table's last row is the catch. A supplier that delivered 80% of its housings on time in week 4 (2,880 of 3,600) cannot build eight extra weeks of them without extra hours, and the administrator will want those hours paid for. If the administrator asks a surcharge of EUR 1.20 a housing for the extra hours (Example data), the buy costs 28,800 x 1.20 = EUR 34,560 more, which sits inside the range of the waiting it prevents. The plant's own margin per caliper, rather than an industry range, decides which side of that range it lands on.
Step 7: what to do first. Take the margin out of the industry range: enter line 3's selling price and margin for each caliper type, and price the minutes at those. Then ask the administrator for a weekly build plan for the housings, and set the buy at the volume the supplier can make on top of the weekly call-off, with the gap covered by the second source's approval date. Split the waiting by shift as well: if one shift waits more, the deliveries arrive at the wrong time of day, which a changed delivery slot fixes faster than any buffer.
Two caveats. The margin is a share of sales, so it understates the loss when the line's fixed costs keep running while it waits; a contribution margin from the plant's own figures is the right number to use. And lost calipers can sometimes be recovered with extra shifts, which turns lost margin into overtime cost; the risk of stopping the OEM's line is not priced in either case.
Book a demo and see losses per line and shift.
Support, resource, buy ahead or buy out: choosing
The cases show four exits, and the worked example adds the measures that decide between them.
| Option | Choose it if | Cost anchor on this page | Watch for |
|---|---|---|---|
| Support the supplier (surcharge, advance payment, loss cover) | Deliveries are stable or improving week on week, and the part has no second source in time | Example surcharge EUR 34,560 over eight weeks; in the Bohai and Schlote cases, millions over more than a year | Support that runs on without a buyer, as both releases of 28 September show |
| Last-time buy, then resource | The supplier has capacity beyond the weekly call-off, and a second source can be approved within the buffer | EUR 907,200 tied up; EUR 1,849.29 to 2,721.60 interest over eight weeks | A buy the supplier cannot build; housings left over if the part changes |
| Resource without a buffer | The second source is close to approval and waiting minutes are low | EUR 13,274.15 to 37,083.34 margin at risk over eight weeks at week 4's rate | Waiting that grows faster than the approval moves |
| Buy the business or the line | The parts are critical, the supplier's know-how and tools are hard to replace, and the administrator is selling | Not priced here; the administrator's sale process sets it | Buying the cost problem with the plant, as falling volume did at Bohai |
Questions to put to the administrator, in writing:
- Is a general prohibition on disposal in place, or are dispositions subject to the administrator's consent, and who signs delivery agreements now?
- Until which date are wages covered, and is the pre-financing of Insolvenzgeld agreed?
- What is the weekly build plan for each part number supplied, and what extra volume could be built for a last-time buy, at what price?
- Once proceedings open, will the administrator perform the delivery contract under InsO § 103, and when will that be declared?
- Which tools, gauges and fixtures in the supplier's plant are recorded as the customer's property, and on which documents?
- Is an investor process running, and by which date does it need the customer's commitment on volumes?
Before any of these, a supplier audit checklist visit to the plant shows what the releases cannot: how many machines run, on how many shifts.
The tools at the supplier: ownership before the move
A resourced part needs its tools. Under InsO § 47, a customer that can show a tool does not belong to the estate can claim it back as its own, and that claim follows ordinary law, not the insolvency. In practice the claim stands or falls on the paperwork, so the check comes before the move, not during it.
| Check | Where to find it | Why it matters |
|---|---|---|
| Tool loan agreement signed | Purchasing file, signed by both companies | Records the tool as the customer's property, lent to the supplier |
| Tool paid for, with invoice | Accounts payable, tooling invoices and amortisation per part | Shows whether the tool was paid in full or is still amortised in the part price |
| Tool marked in the plant | Nameplate or marking on the tool, photographed | Lets the administrator's team identify the tool without dispute |
| Tool listed by number | Customer's tool list against the supplier's asset register | A tool on both lists is the one to settle first |
| Gauges, fixtures and spare inserts | Same documents, item by item | A tool that moves without its gauges cannot be approved at the new source |
Once the tools move, the second source still has to be approved for the part; the steps are in the PPAP production part approval process guide. The waiting minutes from the worked example are the measure of how long the plant can afford that approval to take. When the supplier closes a plant rather than filing, the bank build, the PPAP for the new location and the run at rate are covered in the tracker of auto supplier plant closures.
A four-week watch on an insolvent supplier
Each step produces a number for the decision. Plant, production, purchasing and supplier quality managers can split them as the plant runs.
This week
- List every part number bought from the insolvent supplier, with the lines it feeds and the stock on hand in days.
- Add a stop reason "waiting for parts" with a second level for this supplier and each of its parts, and brief the operators on all shifts.
- Start an on-time-in-full log by delivery: due date, quantity due, quantity received, time received.
- Write to the administrator with the questions above, starting with the wage cover and the build plan.
Over the next four weeks
- Sum the waiting minutes by week and by shift, and convert them to parts not built at the line's rate.
- Price them with each product's selling price and margin, not an industry average.
- Collect the tool documents and reconcile the tool list with the supplier's asset register.
This quarter
- Compare the waiting cost with the cost of a last-time buy at the volume the supplier can build, and with any support the administrator asks for.
- Set the second source's approval date and size the buffer to it.
- Repeat the comparison every week until the decision is taken, because the supplier's reliability is the number that moves.
The same habit helps before any filing: a supplier whose on-time-in-full falls for several weeks while waiting minutes rise is showing the pattern of the worked example, whether or not a court is involved. The wider case for keeping that view is made in supply chain resilience in manufacturing, and the price of each minute in cost of downtime per minute.
The record behind the decision
Every decision on this page turns on one record kept on the customer's lines: the minutes each supplier's parts cost, by line, shift and part, priced in money, and the delivery record beside it. An insolvency notice says the supplier is in trouble. The record says what that trouble costs and how fast it is growing. The same shift record bounds the population when a supplier's part is recalled, as the automotive supplier recalls tracker shows at a retaining ring station.
Fabrico is a cloud OEE and light MES platform. It shows OEE and losses by machine, line and shift, with data from the machine's PLC or an IoT device with sensors on the machines you connect, and operators give the reason for a stop at the machine. With the selling price and margin of each SKU entered, losses are priced in money, so a stop reason such as "waiting for parts: housings, supplier X" sums the minutes and the money an unreliable supplier costs the line. On manual stations, AI cameras (an add-on) count output. Supplier records, purchasing, tool registers and contracts stay in the ERP or the purchasing system. The building blocks are OEE software and a light MES for the production record.
Book a demo and see OEE and losses per line and shift.
What people ask next
What happens to deliveries when a German supplier files for insolvency?
They do not stop on the day of the filing. The court orders provisional measures under InsO § 21, and where it imposes a general prohibition on disposal, the provisional administrator has to continue the business until the court decides on opening (InsO § 22), unless the court agrees to a shutdown. Deliveries go on, but their reliability can change week by week, so track on-time in full by part number from the first day.
How long does Insolvenzgeld cover wages?
SGB III § 165 gives employees Insolvenzgeld for the three months of the employment relationship before the insolvency event, such as the opening of proceedings. The Federal Employment Agency pays it as a rule at the level of net pay, with caps for higher earners, and the application is due within two months of the opening. KARL KLINK's release of 10 November 2026, for example, says wages are secured to the end of the year.
Can the insolvency administrator refuse to perform a supply contract?
Yes, once proceedings are opened. Under InsO § 103 the administrator may perform a mutual contract that neither side has fully performed, or refuse it, in which case the other party's claim is only an insolvency claim. If the customer asks, the administrator has to declare the choice without delay, so ask in writing.
Who owns the tools at an insolvent supplier?
Whoever can show it. Under InsO § 47, a party that can show an item does not belong to the estate can claim it back, under the law that applies outside insolvency. For a customer that means a signed tool loan agreement, the tooling invoices, a marking on the tool and a tool list that matches the supplier's asset register.
Is a last-time buy from an insolvent supplier worth it?
Compare it in money with the waiting it prevents. In the Example plant on this page, an eight-week buy of 28,800 housings ties up EUR 907,200 and costs EUR 1,849.29 to 2,721.60 in interest at ECB rates, against EUR 13,274.15 to 37,083.34 of margin from eight weeks of waiting at the latest week's rate. It only works if the supplier can build the extra volume on top of its weekly deliveries.
How many companies filed for insolvency in Germany in 2026?
Destatis counted 17,252 company insolvency filings from January to August 2026, 6.6% more than a year earlier, and 2,067 in August, up 4.4% (release of 13 November 2026). Filings enter the statistic only after the court's first decision, and Destatis notes that the filing itself often came nearly three months earlier.
Sources
All sources accessed on 18 November 2026. Dates are release or publication dates where a page gives one; other dates are labelled as what they are.
- Schultze & Braun (via presseportal.de), KARL KLINK: Geschäftsbetrieb des Spezialisten für Räumtechnik-Maschinen und -Werkzeuge läuft nach Insolvenzantrag weiter, release dated 10 November 2026
- Brinkmann & Partner, Weber Magdeburg GmbH stellt Antrag auf Eröffnung eines Insolvenzverfahrens, release dated 16 October 2026
- Brinkmann & Partner, Harzgerode: Bohai-Werk und Schwestergesellschaften müssen Geschäftsbetrieb einstellen, release dated 28 September 2026
- Brinkmann & Partner, Schlote-Werke in Harzgerode und Wernigerode beenden Ende Januar ihre Produktion, release dated 28 September 2026
- Insolvenzordnung (InsO) § 21, Anordnung vorläufiger Maßnahmen (gesetze-im-internet.de, Federal Ministry of Justice), current text, undated page
- Insolvenzordnung (InsO) § 22, Rechtsstellung des vorläufigen Insolvenzverwalters, current text, undated page
- Insolvenzordnung (InsO) § 47, Aussonderung, current text, undated page
- Insolvenzordnung (InsO) § 103, Wahlrecht des Insolvenzverwalters, current text, undated page
- Insolvenzordnung (InsO) § 270, Grundsatz (Eigenverwaltung), current text, undated page
- Sozialgesetzbuch III (SGB III) § 165, Anspruch (Insolvenzgeld), current text, undated page
- Bundesagentur für Arbeit, Insolvenzgeld: Informationen für Arbeitgeber, undated page
- Statistisches Bundesamt (Destatis), Unternehmensinsolvenzen im August 2026: +4,4 % gegenüber August 2025 (Pressemitteilung Nr. 398), release dated 13 November 2026
- European Central Bank, Key ECB interest rates, rates with effect from 16 September 2026
- European Central Bank, Euro area bank interest rate statistics: September 2026, release dated 2 November 2026
- Aswath Damodaran, NYU Stern School of Business, Operating and Net Margins by Industry Sector (United States), data as of January 2026