Equipment Commissioning Checklist: Stages, Sign-Offs and Pass Marks

Equipment Commissioning Checklist: Stages, Sign-Offs and Pass Marks

Commission a new packaging machine or line stage by stage, with who signs, the evidence to file and a measured OEE run before the integrator leaves.
Equipment Commissioning Checklist: Stages, Sign-Offs and Pass Marks

In short: An equipment commissioning checklist takes a new machine or line from mechanical completion to a signed handover through five gated stages: mechanical completion, pre-commissioning, cold commissioning, wet commissioning and a performance run. Each check names who signs, the evidence and the pass mark, and the last gate is a measured OEE baseline run.

  • Close each stage with a signature, evidence on file and a pass mark agreed before the work starts.
  • Run the handover test with the plant crew for three shifts in a row, measured from the machine signal or a counting camera.
  • Do not sign until the count is checked, the machine states are logged and stop reasons are in use.
  • A failure-mode table prices the commissioning misses that cost money after handover.

A new flow wrapper, case packer or full packaging line is bolted down, wired and piped. The builder passed its tests, the integrator wants a signature and sales has a launch date. This checklist covers the weeks in between: what to check at each stage, who signs, what goes in the file, and the pass mark that closes the gate.

The factory acceptance test (FAT) at the builder's works and the site acceptance test (SAT) are the stages before commissioning; the acceptance test guide sets out what each one covers. The weeks after handover are a separate plan: the new line ramp-up plan. Machine safety and legal duties are signed off by the plant's own safety and legal owners; this page is not legal advice.

Equipment commissioning checklist: the stages and their gates

The International Electrotechnical Commission's commissioning standard for process plants, IEC 62337, frames the job well. Its summary says it describes activities following the "completion-of-erection" milestone of the project and prior to the "acceptance-of-the-plant" phase by the owner, and that those activities need adapting to each plant. A packaging line is not a process plant, but the shape holds: commissioning starts when the installers say they are done and ends when the owner accepts.

For a food or FMCG packaging machine, five gates do the work: mechanical completion (installed to the drawings, with no A items, the faults that block safe power-on, on the punch list), pre-commissioning with the power off, cold commissioning powered but without product, wet commissioning with product and packaging material, and a performance run by the plant's own crew that ends in handover.

Decide in the commissioning plan who leads each stage, integrator or plant, and where the lead passes from one to the other. A stage nobody owns is a stage nobody closes.

The handover gate is the easiest one to let slide. "It ran well on Thursday" is an opinion. A measured run is not: OEE software reading the machine's own signal, or a camera that counts output where there is no clean signal, records availability, performance and quality per shift, with stops timed and given a reason at the line. The same screen then follows the line after handover, so the first weeks of output are judged on the same rules as the run.

What you see: a shift timeline, unclassified time waiting for a reason, and the operator's line-down screen, on sample lines. Book a demo.
Plays from YouTube. Google may set cookies when you press play. Privacy policy.

Commissioning stage gates: pass mark met, sign and move on; not met, punch list, fix and retestStage 1 mechanical completion: installed to drawings, punch list A empty. Stage 2 pre-commissioning: power off checks of wiring, air, safety file and hygiene. Stage 3 cold commissioning: powered with no product, I/O, safety functions and dry cycles. Stage 4 wet commissioning: product and film, formats, count and changeover. Stage 5 performance run: plant crew, 3 shifts, measured OEE baseline. Each gate: yes, sign and go on; no, punch list, fix, retest. Then handover signed.Five stages, five gates1. Mechanical completionInstalled to the drawings,no A items on the punch listNo: punch list,fix, retestYes: sign, go to the next gate2. Pre-commissioningPower off: wiring, air,safety file, hygiene planNo: punch list,fix, retestYes: sign, go to the next gate3. Cold commissioningPowered, no product: I/O,safety functions, dry cyclesNo: punch list,fix, retestYes: sign, go to the next gate4. Wet commissioningProduct and film: formats,count, rejects, changeoverNo: punch list,fix, retestYes: sign, go to the next gate5. Performance runPlant crew, three shifts,measured OEE baselineNo: punch list,fix, retestYes: sign, go to the next gateHandover signed: baseline on file,signals and reasons in use
Each stage ends at a gate: pass mark met, sign and move on; missed, the item goes on the punch list and is retested.

The safety and legal layer, before first power-on

In the EU, the machine arrives with duties already met by its maker. The Machinery Directive 2006/42/EC, Article 5, says that before placing machinery on the market and/or putting it into service, the manufacturer or an authorised representative must, among other things, draw up the EC declaration of conformity and affix the CE marking. Check both are in the file, with instructions in the plant's language, before anyone powers the machine. Where a line joins machines from several makers, ask who declares the line as a whole.

The rules are changing. The new Machinery Regulation (EU) 2023/1230 replaces the Directive. The European Commission notes that a corrigendum fixed its application dates, and that machinery placed on the EU market before 20 January 2027 must comply with Directive 2006/42/EC. A line ordered now may be put into service either side of that date, so ask the builder which law the machine was built and declared to.

Risk assessment has its own standard. ISO 12100 specifies principles of risk assessment and risk reduction for the design of machinery; ask for the builder's assessment, and add the hazards your layout creates, such as a new walkway or an operator reaching into a buffer.

The plant also has duties as the user. In Great Britain, HSE guidance says that where safety depends on how equipment is installed, it should be inspected after installation and before first use. In the US, OSHA's lockout standard, 29 CFR 1910.147, requires an energy control program of procedures, training and periodic inspections before anyone services a machine that could start up unexpectedly. Commissioning has plenty of that work: guards come off, settings change, and two teams work on one machine. OSHA's overview is blunt that the unexpected startup or release of stored energy can result in serious injury or death. Write the isolation procedure for each energy source on the new machine before cold commissioning, not after the first incident. More on the practice: lockout tagout.

The checklist with pass marks, stage by stage

Three tables cover the first four stages; the fifth, the handover, has its own section below. Each row is a check, the person who signs it, the evidence that goes in the file and the pass mark that closes it. Agree the pass marks in the commissioning plan before the integrator arrives; a pass mark written on the day of the test tends to match whatever the line just did. Change the names to the roles your plant uses, but keep one name per row.

Stages 1 and 2: mechanical completion and pre-commissioning

CheckWho signsEvidencePass mark
Mechanical completion walkdown against the drawingsProject engineer, integrator leadSigned completion record, punch listNo A items open
Electrical and pneumatic install: earthing, insulation tests, air pressureElectrical engineerTest sheets per circuitAll circuits tested, within the builder's limits
Safety file: CE marking, declaration, instructions, risk assessmentPlant safety ownerCopies in the project fileComplete before first power-on
Isolation points and a lockout procedure per energy sourcePlant safety ownerWritten procedure, labelled isolatorsEvery source has a tested procedure
Product-contact parts and cleaning planQA or hygiene leadMaterial declarations, cleaning methodAll contact parts covered

Stage 3: cold commissioning

CheckWho signsEvidencePass mark
I/O check: every sensor and actuatorIntegrator controls engineerTicked I/O list100% of points checked
Safety functions: e-stops, guard interlocks, light curtainsPlant safety ownerFunction test recordEach one stops the machine as designed
Dry cycles at 50%, 75% and 100% of rated speedIntegrator leadSpeed log with timesEach step runs clean for the agreed time
Machine states and counts reach plant systemsPlant automation or IT/OT leadSignal list with timestampsEach state seen once and matches the HMI
Format parameters loaded for every formatIntegrator controls engineerRecipe list per formatAll formats in the contract loaded

The signal row is easy to leave until later. If the machine follows PackML, the OPC Foundation's PackML specification names standard machine states and Overall Equipment Effectiveness (OEE) data as things PackML provides. Ask the integrator to show each state arriving in your systems during cold commissioning, while changes are still cheap. The detail is in the PackML state model guide, and what a machine screen can and cannot give you is in HMI data collection for OEE.

Stage 4: wet commissioning

CheckWho signsEvidencePass mark
First runs per format with film and cartons from normal suppliersProduction managerRun log per formatOne clean hour at rated speed per format
Count at the constraint against a hand countCI or production engineerHand tally sheet, counter readingWithin 1% over one hour
Rejects reach the bin and the reject countQA leadBin count against the reject counterCounts match
Changeover per format against its standardProduction managerTimed changeover sheetTwo in a row within the standard
Cleaning or washdown cycleQA or hygiene leadCleaning validation recordQA signs it off
Stop reason list on the operator screen, crews trainedProduction managerReason list, training record per shiftEvery shift trained before the performance run

Two rows decide whether the handover data can be trusted: the hand count proves the counter, and the reason list decides whether the run's stops can be split between builder and plant. Keep that list short, with builder and plant items apart; downtime reason code design covers how.

The handover test: a measured OEE baseline run

The performance run turns "it works" into a number both sides sign. The formula need not be invented: a NIST report on manufacturing standards notes that ISO Standard 22400 presents commonly-accepted OEE calculations, including the timing calculations. Use it for the run, with one formula written into the plan: OEE is availability times performance times quality, with losses counted once at the constraint, as in the OEE calculation guide.

Eight pass marks close the gate. Do not sign while any is open:

  1. Run length: 3 shifts in a row, nights and a changeover.
  2. Crew: Plant operators run it; integrator only advises.
  3. Count: Counter within 1% of a one-hour hand count.
  4. States: Running, stopped, starved, blocked, faulted logged.
  5. Reasons: Reason list live; unclassified 10% or less.
  6. OEE baseline: A, P and Q at or above the plan's marks.
  7. Punch list: No A items; B items dated, with an owner.
  8. Dossier: Drawings, PLC backup, spares, training records.

If the line has a contract performance figure, the test conditions for it belong in the contract, not here; see the OEE clause in a new line contract. The baseline run is the plant's own measurement, and it becomes week 0 of production. How to set a baseline that holds is covered in OEE baseline measurement.

Commissioning handover card: sample OEE baseline run, count check and unclassified stops, then 8 pass marks before sign-off
The sample handover run in three numbers, then the eight pass marks that close the last gate. Sample figures for illustration only.
Text version of this infographic
  • Title: Equipment commissioning: the handover gate. One measured run, then 8 pass marks.
  • OEE: 75.4% baseline over a 3-shift run (87.0% availability, 88.0% performance, 98.5% quality). Pass mark: 70%.
  • Count: +0.4% against a hand count over one hour. Limit: 1%.
  • Reasons: 15.0% of stop time unclassified. Limit 10%, so one shift is rerun.
  • Sample figures for illustration only.
  • Measure the run, then sign.
  • 8 pass marks before sign-off:
  • 1. Run length: 3 shifts in a row, nights and a changeover.
  • 2. Crew: Plant operators run it; integrator only advises.
  • 3. Count: Counter within 1% of a one-hour hand count.
  • 4. States: Running, stopped, starved, blocked, faulted logged.
  • 5. Reasons: Reason list live; unclassified 10% or less.
  • 6. OEE baseline: A, P and Q at or above the plan's marks.
  • 7. Punch list: No A items; B items dated, with an owner.
  • 8. Dossier: Drawings, PLC backup, spares, training records.

Worked example: the handover run on a biscuit flow-wrap line

Sample figures for illustration only. A biscuit plant commissions a new flow-wrap line. The flow wrapper is the constraint, rated at 150 packs a minute for the format tested. The plan sets the run at three shifts in a row of 480 minutes, so 1,440 planned minutes, with one changeover and the night shift included. The pass marks, written before the run: availability 85%, performance 85%, quality 98%, OEE 70% (85% x 85% x 98% = 70.8%, rounded down), unclassified stop time 10% or less of stop time, and the counter within 1% of a hand count.

What the run recorded:

  • Stops: 187 minutes. Changeover 38, machine faults 96 (film splices and infeed jams), starved by the biscuit feed 25, and 28 with no reason.
  • Availability: run time 1,440 minus 187 = 1,253 minutes. 1,253 / 1,440 = 87.0%.
  • Performance: 165,400 packs counted against 1,253 x 150 = 187,950 possible. 165,400 / 187,950 = 88.0%.
  • Quality: 2,480 rejects, so 162,920 good packs. 162,920 / 165,400 = 98.5%.
  • OEE: 87.0% x 88.0% x 98.5% = 75.4%. Check: 162,920 good packs / (1,440 x 150 = 216,000) = 75.4%.
  • Count check: over one hour, the counter read 8,445 and the hand count 8,412: +0.4%, inside the limit.

Four OEE marks pass. The reasons mark does not: 28 of 187 stop minutes, 15.0%, have no reason. So the line is not handed over yet. The integrator and the crew go through the 28 minutes with the shift notes, fix the reason list where it had no fitting entry, and rerun one shift.

In money. At a sample contribution of EUR 0.12 a pack, one minute of the wrapper standing costs 150 x EUR 0.12 = EUR 18, and an hour EUR 1,080. Against the 216,000 packs the run could have made, it lost 53,080: 28,050 to stops (187 x 150), 22,550 to slow running (187,950 minus 165,400) and 2,480 to rejects, each counted once. That is EUR 6,369.60 over three shifts. The 28 unclassified minutes alone are EUR 504 a run; over 15 shifts a week, if nothing changes, EUR 2,520 a week of loss that no one can assign to the builder or the plant.

If the counter had never been checked. Say it over-read by 3%. The true count would be about 160,583 packs, performance 160,583 / 187,950 = 85.4%, good packs 158,103 and OEE 158,103 / 216,000 = 73.2%. The run still passes 70%, but the baseline sits 2.2 points high, and every week after handover would chase a number the line never made. The 4,817 phantom packs are worth about EUR 578 a run and EUR 2,890 a week.

Sample handover run: four OEE pass marks met, unclassified stop time over its limit, so no signature yetSample figures for illustration only. Availability 87.0% against a pass mark of 85%. Performance 88.0% against 85%. Quality 98.5% against 98%. OEE 75.4% against 70%. Unclassified stop time 15.0% of stop time against a limit of 10%: fail. Counter against hand count: +0.4%, limit 1%: pass.Handover run vs pass marksSample figures for illustration onlyAvailability: 87.0% (pass ≥85%)PassPerformance: 88.0% (pass ≥85%)PassQuality: 98.5% (pass ≥98%)PassOEE: 75.4% (pass ≥70%)PassUnclassified stop time: 15.0% (pass ≤10%)FailCounter vs hand count: +0.4% (pass within 1%)Verdict: fix reasons, rerun one shift
Sample figures for illustration only. Good OEE is not enough to sign: the stop reasons failed their mark, so one shift is rerun.

Commissioning misses that cost money after handover

Each miss below can pass a handover unnoticed and surface weeks later as lost output. Here are seven, with the first sign in the line data and a sample cost at EUR 18 a minute, the flow-wrap example's rate. Sample figures for illustration only.

Commissioning missFirst sign in the line dataSample costClose it before handover
No stop reason list at handover15% or more of stop time has no reasonEUR 2,520 a week of stops nobody can assignLoad the list and train each shift in wet commissioning
Counter never checked against a hand countOEE reads high; packed output does not match the count3% over-read hides about EUR 2,890 a weekOne-hour hand count, within 1%
Rated speed per format not written downPerformance swings when someone edits the rateRate set to 140 instead of 150: 12,530 packs of slow running hidden, EUR 1,504 per three shiftsRated speed per format in the handover file
Changeover not timed before handoverChangeovers run 20 minutes over the standard5 a week: EUR 1,800 a weekTwo timed changeovers per format
Critical spares not on siteOne long stop waiting for a partOne 8-hour wait: EUR 8,640Spares list agreed and stocked before handover
Crews trained on the day shift onlyNight shift stops run longer30 more minutes a night, 5 nights: EUR 2,700 a weekTrain each shift; include nights in the run
Film tested from one supplier onlyJams when the second supplier's reel goes on135 extra stop minutes in one run: EUR 2,430Wet runs with every approved supplier's material

Each fix costs an hour or a shift while the integrator is on site, and weeks once its engineers have gone home. Watch the speed row: if the rated speed per format is not on file, it can be edited down later, and slow running leaves the figures but not the line. Reduced speed vs minor stops explains how to tell them apart.

Book a demo to see stops, counts and reasons from a connected line laid out on one shift timeline, the view a handover run is read from.

Plan it this week, close it this quarter

For a plant, production or engineering manager with a machine arriving in the next few months:

  1. This week: write the five gates into the commissioning plan with one owner each, and name who leads which stage, integrator or plant.
  2. This week: set the performance run pass marks (run length, crew, OEE factors, unclassified limit, count tolerance) and send them to the integrator.
  3. This week: ask the builder for the declaration of conformity, instructions and risk assessment.
  4. This month: draft the stop reason list for the new machine, split into builder and plant items, and decide where the count and the machine states will come from.
  5. This month: agree the critical spares list and the training plan per shift, night shift included.
  6. This quarter: run the four stage tables, file the evidence, and hold the handover until all eight pass marks are met.
  7. This quarter: carry the baseline into week 1 of production unchanged, with the same formula, rated speed and reason list.

For a new site rather than a new line, maintenance software set-up runs alongside this work; see CMMS for a greenfield plant start-up as a further read.

Where Fabrico helps at the handover gate

Fabrico is OEE and light MES software. At commissioning, it supplies the measured side of the last gate:

  • The baseline from the machine: Fabrico reads automated machines from the PLC and fits an IoT device with sensors where the PLC is hard to read, so the run is measured in availability, performance and quality per machine, line and shift.
  • Stops with reasons: micro-stops are detected from the machine signal, and the operator picks the stop cause on a tablet or phone, so the unclassified share is visible during the run, not after it.
  • A machine with no usable signal: the camera add-on counts output instead, and its video for a stop is streamed on request and not stored in Fabrico.
  • Evidence for the file: downtime splits by cause, machine and shift, losses are shown in money, and lists export to Excel or CSV for the handover report.

More: the OEE and MES solution overview, light MES explained, the computer vision add-on, how to judge OEE software, OEE software for high-speed packaging lines and computer vision for food manufacturing. Flow wrapper losses in detail: flow wrapper OEE.

Questions engineers ask about commissioning

Where does commissioning start and end?

It starts at mechanical completion, when the installers say the machine is in place to the drawings, and ends when the plant signs the handover. In between, the installed machine is checked stage by stage, from power-off checks through dry and product runs to a performance run by the plant's own crew. The builder's acceptance tests come before it.

What is the difference between cold and wet commissioning?

Cold commissioning runs the machine powered but without product: I/O checks, safety functions and dry cycles at rising speed. Wet commissioning adds product, packaging material and, on food lines, water or cleaning fluids, so formats, counts, rejects and changeovers can be tested for real.

How long should the performance run before handover be?

At least three shifts in a row, with the night shift, one changeover and the formats that matter. If one shift misses a pass mark, fix the cause and rerun that shift; do not average it into the other two.

Who should sign the commissioning handover?

The production manager accepts the line for output, the engineering manager accepts the technical file and punch list, the plant's safety owner signs the safety checks, and the integrator's project lead signs for the supplier. Each signature sits next to the evidence it covers.

Do I need OEE software to commission a new packaging machine?

Not to commission it, but the handover test needs a measured baseline: availability, performance and quality taken from the machine signal, with stop reasons logged. A spreadsheet can do it on one run; software keeps the same rules through the weeks that follow.

Book a demo to see a measured run on one screen: availability, performance and quality by shift, with stops and their reasons.

Track OEE and downtime in real time
See where lines lose time
Book a live demo.
See where lines lose time
See where lines lose time

Real Fabrico tiles, sample data.

By clicking the Accept button, you are giving your consent to the use of cookies when accessing this website and utilizing our services. To learn more about how cookies are used and managed, please refer to our Privacy Policy and Cookies Declaration